Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/09/2019 | PLUMBING - FINAL | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED | |
| 05/07/2019 | PLUMBING - FINAL | Partial Approval | Chlorination Report submitted and need to be approved. Ok to issue Certificate of Occupancy. Permit ok to close pending engineering Inspection. | |
| 04/26/2019 | PLUMBING - FINAL | Partial Approval | 4th floor guest rooms ok to occupy upon issuance of c of o | |
| 04/25/2019 | PLUMBING - FINAL | Partial Approval | All 2nd floor guest rooms ok for occupancy upon c of o | |
| 04/24/2019 | PLUMBING - FINAL | Partial Approval | All 1st floor guest rooms ok to occupy. 4th floor hall ceiling ok to cover. Garbage truck pre dumpster pad, 20x20 with #4 grid at 10” o.c. Ok to pour. |