Permit: T16CM07308

Parcel: 141220250


Addresses:

9095 S RITA RD


Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T16CM07308

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
04/22/2019 FRAMING Approved See notes for 1036 Building Above Ceiling
04/17/2019 FRAMING Not ready for Inspection Inspection called in for 4th floor above ceiling, work incomplete upon arrival.
04/16/2019 FRAMING Partial Approval 3rd floor hallway above grid ok to complete drop ceiling
04/04/2019 FRAMING Partial Approval 2nd floor hall above grid ok to complete drop ceiling
03/15/2019 FRAMING Partial Approval 2nd, 3rd, and 4th floor hard lid rooms ok to rock
03/11/2019 FRAMING Partial Approval All 1st floor lids ok to cover
03/06/2019 FRAMING Partial Approval ok to close ceiling on 1st floor for sales, manager, and work station rooms
12/21/2018 FRAMING Partial Approval Elevator shaft fire tape ok
12/05/2018 FRAMING Partial Approval All guest rooms on the second floor, west of elevator, OK to rock.
12/04/2018 FRAMING Partial Approval 1st floor guest room drop ceilings ok to rock.
11/30/2018 FRAMING Not ready for Inspection WORK INCOMPLETE
11/19/2018 FRAMING Partial Approval 4TH FLOOR CLIPS AND SHEARS OK.
11/14/2018 FRAMING Partial Approval 1- Entire 4th floor shear wall nailing is okay.
2- 1st floor west of the elevator shaft to the end of the bldg, ceilings and walls are okay to cover, all trades approved.
11/08/2018 FRAMING Partial Approval 1- 1st floor from east of elevator shaft to end of bldg. all trades approved and okay to cover.
10/16/2018 FRAMING Partial Approval 1- 4th floor deck nailing is okay from the elevator shaft west to end of bldg
10/11/2018 FRAMING Partial Approval 1- 4th floor deck nailing is okay from the elevator shaft all the way to the east end of building only.
10/02/2018 FRAMING Partial Approval IVRS - Inspection :*
1- 3RD FLOOR EXTERIOR SHEAR WALL NAILING IS OKAY.
09/10/2018 FRAMING Partial Approval IVRS - Inspection :*
1- 3R FLOOR DECK NAILING IS OKAY WEST OF THE ELEVATOR SHAFT TO THE WEST END OF BLDG.
09/06/2018 FRAMING Partial Approval IVRS - Inspection :*
1- 3RD FLOOR DECK NAILING IS OKAY FROM THE EAST EXTERIOR WALL TO THE ELEVATOR SHAFT.
08/22/2018 FRAMING Partial Approval IVRS - Inspection :*
1- 1ST FLOOR SHEAR WALL PANELS LOCATED FROM GRID LINE #1 THRU #6 ARE OKAY.
08/10/2018 FRAMING Partial Approval IVRS - Inspection :*
1- HOLD DOWNS PROVIDED AND SET IN PLACE FROM GRID LINE 1 THRU GRID LINE 6.
08/01/2018 FRAMING Not ready for Inspection FRAMING INSPECTION CALLED IN, BUT IT WAS REALLY A EXT METAL CLIPS AND SHEATHING INSPECTION. SEE NOTES THERE
07/30/2018 FRAMING Partial Approval IVRS - Inspection :*
07/27/2018 FRAMING Cancelled SUPER CANCELED, TILL MON
06/06/2018 FRAMING Not ready for Inspection SUPER NEEDS REGULAR INSPECTOR BILL JONES TO CHECK IN AS IT HAS BEEN A WHILE SINCE LAST INSPECTION, AND SUPER JUST WANTS TO MAKE SURE HE IS ON THE SAME PAGE AS THE INSPECTOR AS HE PROCEEDS.