Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T11CM00766
Permit Details
Apply Date:
03/14/2011
Applicant:
N/A
Description:
RETAIL
Architects:
- HILL, MARTIN LEE
Contractors:
- TL ROOF AND ASSOCIATES
Permit Reviews
Permit Number - T11CM00766
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/14/2011 | COMMERCIAL - TI | 03/29/2011 | COMPLETED |
03/29/2011 | COMMERCIAL - TI | 04/27/2011 | COMPLETED |
05/05/2011 | RESUBMITTAL | 06/06/2011 | COMPLETED |
06/06/2011 | RESUBMITTAL | 06/10/2011 | COMPLETED |
08/16/2011 | REVISION - - 1ST | 08/16/2011 | COMPLETED |
08/16/2011 | RESUBMITTAL | 09/01/2011 | COMPLETED |
09/06/2011 | REVISION - - 1ST | 09/06/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00766
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/14/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00766
Permit Description: RETAIL
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/16/2011 | ELECTRIC - UNDERGROUND | RMYERS | Approved | IVRS - Inspection :* |
07/22/2011 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
07/26/2011 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED PER R. HOLLANDER |
07/29/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
08/03/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
08/03/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
08/03/2011 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
08/05/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
08/05/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
08/23/2011 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
09/12/2011 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* |
09/12/2011 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
09/12/2011 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
09/13/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
09/13/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
09/13/2011 | RIGHT OF WAY - FINAL | M.Otero | Approved | |
09/13/2011 | NPPO - FINAL | MRUSSO | Approved | |
09/13/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
09/13/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
09/13/2011 | SIGN - FINAL | MRUSSO | Approved | |
09/14/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) DUCT SMOKE DETECTORS TESTED BY FIRE ALARM COMPANY 2) OK FOR FINAL 3) GAS FLEX CONNECTORS OK |
09/15/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
09/15/2011 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
09/16/2011 | FIRE - ALARM FINAL | DSIWARI | Approved | PER INSP CARD |
09/16/2011 | FIRE - FINAL | DSIWARI | Approved | PER INSP CARD |
09/16/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
09/21/2011 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | |
09/21/2011 | ELECTRIC - PROGRESS | RHOLLAND | Approved | |
09/21/2011 | ELECTRIC - UFER | RHOLLAND | Approved | |
09/23/2011 | ELECTRIC - FINAL | LHANLY | Approved | BALING MACHINE OK. UL CONTROL PANEL, MECHANICAL ASSEMBLY INSPECTED BY PROFESSIONAL ENGINEER AT ASSEMBLY PLANT. ELECTRICAL CONNECTIONS AND CONTROLS OK. |
09/26/2011 | CERTIFICATE OF OCCUPANCY | LHANLY | Approved | |
09/26/2011 | BUILDING - FINAL | LHANLY | Approved |