Permit: T10CM02391
Permit Details
Status:
Final
Type:
COMMERCIAL OTHER
Address:
275 N COMMERCE PARK LP
Address NEW:
275 N COMMERCE PARK LP
Apply Date:
08/27/2010
Applicant:
N/A
Description:
FOUNDATION ONLY FOR FUTURE NEW OFFICE BUILDING AND GARAGE " Q I P"
Contractors:
- SUNDT CONSTRUCTION
Permit Reviews
Permit Number - T10CM02391
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR FUTURE NEW OFFICE BUILDING AND GARAGE " Q I P"
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/12/2011 | RESUBMITTAL | 01/13/2011 | COMPLETED |
| 08/27/2010 | PLANS OK TO SUBMIT - COMM | 09/01/2010 | COMPLETED |
| 09/01/2010 | COMMERCIAL NEW | 10/06/2010 | COMPLETED |
| 11/03/2010 | RESUBMITTAL | 12/01/2010 | COMPLETED |
| 12/06/2010 | RESUBMITTAL | 12/29/2010 | COMPLETED |
| 12/30/2010 | RESUBMITTAL | 01/12/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM02391
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR FUTURE NEW OFFICE BUILDING AND GARAGE " Q I P"
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/27/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM02391
Permit Description: FOUNDATION ONLY FOR FUTURE NEW OFFICE BUILDING AND GARAGE " Q I P"
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2011 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
| 06/06/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* MIKE RUSSO WILL DO STORMWATER GRADING RICKY MEYEERS WILL LOOK AT ROOF DRAINS AND OVER FLOW |
| 06/20/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) ASD-006 CHANGE ORDER ADA ACCOMADATIONS 2) OFFICE UNDER SLAB OK |
| 06/27/2011 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1) OK TEMP TO SUN MECH TRAILER 2) OK 1ST LIFT ROOMS ANNEX AREA 3) OK STUBS AT V3F 4) OK GROUNDING GEN PAD |
| 06/30/2011 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* 1) STEM AT VISITOR CENTER OK |
| 06/30/2011 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/08/2011 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* 1) OK CADWELD TO COLUMN FOR LIGHTING 2) OK 2ND LIFT BLOCK WALLS |
| 07/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* 1) RAM WALL AT NORTH SIDE OF VISITOR CENTER |
| 08/16/2011 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* 1) RAMP ON GARAGE |
| 02/02/2012 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK SUBJECT TO CONDITIONS FROM 02/01/12 INSPECTION |
| 02/02/2012 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 02/02/2012 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 02/02/2012 | SIGN - FINAL | MRUSSO | Approved | |
| 02/02/2012 | NPPO - FINAL | MRUSSO | Approved | |
| 02/03/2012 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/03/2012 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/03/2012 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/24/2012 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 02/24/2012 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 02/28/2012 | FIRE - FINAL | FIRE | Approved |