Permit: T10CM02391

Parcel: 116193760

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
02/03/2012 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
07/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) RAM WALL AT NORTH SIDE OF VISITOR CENTER
07/28/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
06/30/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
06/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELECTRIC ROOM
06/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) VISITOR CENTER
06/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* BALLARDS OK LOADING DOCK LEVELER OK PACI
06/13/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
06/06/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* ANNEX AREA OK
05/31/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
05/12/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) DRY PACK ON T-PAC COLUMN PROGRESS AREA
05/11/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) DRY PACK ON COLUMNS IN GARAGE
05/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 6/0-F, 5.6/8.9
05/03/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
04/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
GL 4/I, 6/I. LOADING DOCK AREA
04/26/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/25/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/13/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) WATER PROOFING AT LOADING DOCK
03/21/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/17/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/17/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTINGS, GRADE, BEAMS, COLUMN FOOTINGS (7.0, 7.5, 8.0) GL: 8/A-F, GL: 0/2-7, 0-A/2: DETAILS 2/S201, 2/S200, 3/S202 OK TO POUR PROGRESS AREAS
2) UNSCHEDULED INSPECTION-PLEASE BILL SUNDT ACCOUNT FOR $165.00 FOR INSPECTION
03/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTINGS-GRADE BEAMS, COLUMN FOOTINGS: GL 7-8/0 8/0-G.5 OK TO POUR PROGRESS AREAS. COLUMN FOOTINGS 4 #8.0 AND 4 #7.5
03/11/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELEVATOR #2 FOOTER
03/08/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELEVATOR AND STAIRWELL #3
03/04/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL D-E/4-6
03/01/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL K/G.9-10
02/26/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/25/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/24/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 10 MID RAMP
02/23/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTER ? 9.8 MID RAMP
2) TWO INSPECTIONS AM & PM $165.00 TO BE CHARGED TO AP ACCOUNT
02/22/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) MID RAMP AND NORTH RAMP COLUMNS
02/15/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL F.L7/9-10, F.7-T/13, 1.0/1.5-4
02/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
GL 1.5 - 6.9 /Y V. / 1.5-9 E-F/ 6.9-2
01/26/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) INFO ONLY