Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2012 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 07/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) RAM WALL AT NORTH SIDE OF VISITOR CENTER |
|
| 07/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 06/30/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 06/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELECTRIC ROOM |
|
| 06/27/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) VISITOR CENTER |
|
| 06/14/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BALLARDS OK LOADING DOCK LEVELER OK PACI | |
| 06/13/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 06/06/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ANNEX AREA OK | |
| 05/31/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 05/12/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) DRY PACK ON T-PAC COLUMN PROGRESS AREA |
|
| 05/11/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) DRY PACK ON COLUMNS IN GARAGE |
|
| 05/09/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 6/0-F, 5.6/8.9 |
|
| 05/03/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 04/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/27/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GL 4/I, 6/I. LOADING DOCK AREA |
|
| 04/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/25/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/13/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WATER PROOFING AT LOADING DOCK |
|
| 03/21/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 03/17/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 03/17/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) FOOTINGS, GRADE, BEAMS, COLUMN FOOTINGS (7.0, 7.5, 8.0) GL: 8/A-F, GL: 0/2-7, 0-A/2: DETAILS 2/S201, 2/S200, 3/S202 OK TO POUR PROGRESS AREAS 2) UNSCHEDULED INSPECTION-PLEASE BILL SUNDT ACCOUNT FOR $165.00 FOR INSPECTION |
|
| 03/14/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) FOOTINGS-GRADE BEAMS, COLUMN FOOTINGS: GL 7-8/0 8/0-G.5 OK TO POUR PROGRESS AREAS. COLUMN FOOTINGS 4 #8.0 AND 4 #7.5 |
|
| 03/11/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR #2 FOOTER |
|
| 03/08/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR AND STAIRWELL #3 |
|
| 03/04/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL D-E/4-6 |
|
| 03/01/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL K/G.9-10 |
|
| 02/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 02/25/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 02/24/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 10 MID RAMP |
|
| 02/23/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) COLUMN FOOTER ? 9.8 MID RAMP 2) TWO INSPECTIONS AM & PM $165.00 TO BE CHARGED TO AP ACCOUNT |
|
| 02/22/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) MID RAMP AND NORTH RAMP COLUMNS |
|
| 02/15/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL F.L7/9-10, F.7-T/13, 1.0/1.5-4 |
|
| 02/10/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 02/09/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GL 1.5 - 6.9 /Y V. / 1.5-9 E-F/ 6.9-2 |
|
| 01/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) INFO ONLY |