Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2012 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 06/20/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) ASD-006 CHANGE ORDER ADA ACCOMADATIONS 2) OFFICE UNDER SLAB OK |
|
| 06/15/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) OFFICE BLDG DRAIN CONNECTED TO BLDG SEWER OK |
|
| 06/14/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) K-O AND 5-8 OK TO COVER |
|
| 06/13/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/10/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/08/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) COLUMNS 2-5 AND A-G OK TO COVER 2) B0-THIS IS MY FORTH REQUEST FOR A COMPERHENSIVE PLUMBING PLAN, THAT INCLUDES ALL OF THE PLUMBING TO BE INSTALLED TO DATE |
|
| 06/07/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) VISTOR CENTER UNDER SLAB OK 2) WATER TEST TO 10' OK 3) 4" PVC ROOF DRAIN STUBBED OUT ONLY 4) 2" TYPE WATER SERVICE STUBBED OUT 5' |
|
| 05/26/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) NEW COMPLETE SET OF PLANS NOW AVAILABLE: DOES NOT INCLUDE RFI'S AND RED LINES FROM OLD SET. DOES NOT CONSOLISATE ARCHITECUAL AND PLUMBING PAGES TO GIVE COMPREHENSIVE PLUMBING PAGE 2) REVISION AT COLUMN H AND 8 OK TO COVER |
|
| 05/25/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) TRUCK DOCK AREA DRAIN AS INITIALED ON P200B PLUMBERS PRINT |
|
| 05/20/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) AS REDLINED ON P200B PLUMBERS PLAN OK TO COVER |
|
| 05/16/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) FLAMMABLE WASTE FROM INTERCEPTOR TO COLUMN "S" AND FROM COLUMNS #2-#5 OK TO COVER 2) ? AT COLUMN=2' 3) WATER STUBBED OUT ? ? |
|
| 05/11/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) FLAMMABLE WASTE AT G-2 AS INITIALED ON P200B N/H WITH HUSKEE BANDS-WATER TEST ONE RISER TO TEN FEET 2) INSPECTOR IS STILL WAITING FOR A COMPREHENSIVE PLUMBING PLAN SO HE DOESN'T HAVE TO REFER TO THREE DIFFERENT PAGES TO FIND OUT THE EXTENT OF PLUMBING |
|
| 05/06/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SANITARY WASTE AT S-5 AREA OK TO COVER AS RED LINED ON PLUMBERS PAGE P200B |
|
| 05/04/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) COORDINATE PLUMBING ON ARCHETECTUAIL PAGES WITH THE PLUMBING ON THE PLUMBING PAGES - PROVIDE ONE APPROVED PLAN THAT SHOWS ALL OF THE PLUMBING 2) COLUMNS O-T & 2-5 AS INITIALED ON PZOOB PLUMBERS . OK TO COVER TRUNKLINE, PLUMBING STUBBED UP FOR NOW.PLAN |
|
| 04/22/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 03/31/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | NOT ON LIST FOR ACCESS. |