Permit: T09CM00849
Permit Details
Apply Date:
04/16/2009
Applicant:
N/A
Description:
NEW PRACTICE GYMNASIUM
Architects:
- FROST, MARC CAHILL
Contractors:
- SUNDT CONSTRUCTION
- TUCSON UNIFIED SCHOOL DIST #1 **C
Permit Reviews
Permit Number - T09CM00849
Permit Status: C of o
Permit Description: NEW PRACTICE GYMNASIUM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/16/2009 | PLANS OK TO SUBMIT - COMM | 04/17/2009 | COMPLETED |
| 04/22/2009 | 3RD PARTY REVIEW-COMMERCIAL | 06/04/2009 | COMPLETED |
| 06/04/2009 | POST 3RD PARTY REVIEW | 06/23/2009 | COMPLETED |
| 06/23/2009 | POST 3RD PARTY REVIEW | 06/25/2009 | COMPLETED |
| 09/16/2010 | REVISION - - 2ND | 09/16/2010 | COMPLETED |
| 09/24/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 10/13/2009 | COMPLETED |
| 12/16/2009 | REVISION - - 1ST | 12/22/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00849
Permit Status: C of o
Permit Description: NEW PRACTICE GYMNASIUM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/16/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00849
Permit Description: NEW PRACTICE GYMNASIUM
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 11/06/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | 1) PARTIAL RE-ROUGH AT FOOTING LOCATIONS OK TO COVER |
| 12/17/2009 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* 1) OK LOAD FEEDERS FROM NEW SES AND GENERATOR TO EXIST. GEAR |
| 12/31/2009 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* 1) 8' LIFT GL D-C/11, ROOMS B108,B107 & B1037 |
| 01/14/2010 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* 1) 1-3/0 UFER FO SCS SWITCH GEAR 2) 1-3/0 UFER FOR GENERATOR |
| 02/09/2010 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/26/2010 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* 1) CONTRACTOR TO LOCK OUT-TAG OUT EQUIP. AS NECESSARY-ANY AUTHORIZE PERSONS TO HAVE ACCESS TO ELECTRICAL 2) RECEIVED GFI MAIN SES BREAKER TEST REPORT |
| 04/27/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "MDS" PER D. SANTACRUZ |
| 05/07/2010 | FIRE SPKLR - UG, PIPING, HYDRO | DSiwarski | Approved | Approved |
| 08/23/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) NORTH SIDE DUCTS SECURED |
| 12/15/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 12/15/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 12/15/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 12/15/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 12/15/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 12/29/2010 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER RAIN WATER LEADER 2) YARD WATER INSTALLED WITHOUT INSPECTION, SOME ISSUES ARE: MINIMUM BURIAL DEPTH 12" OF COVER, BLUE TRACER, EXPOSE CONNECTIONS AND FITTINGS 3) CONTRACTOR IS REQUESTING A TEMP C OF O-PLUMBING IS COMPLETE, NOT YET INSPECTED 4) STERILIZATION COMPLETE 5) MAIN ISSUE IS VERIFICATION OF INSTALLATION OF YARDWATER PIPE-THERE IS A DEPTH PROBLEM |
| 12/30/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) ITEMS 1 & 2 DATED 12/16/10 HAVE BEEN CORRECTED |
| 12/30/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/30/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | SIGN - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/30/2010 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
| 12/30/2010 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 12/30/2010 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 12/30/2010 | RIGHT OF WAY - FINAL | M.Otero | Approved | |
| 12/30/2010 | FIRE - FINAL | DSIWARSKI | Approved | Note: Required to retest several smoke detectors in hallway. |
| 12/30/2010 | NPPO - FINAL | JFEMLING | Approved | |
| 12/30/2010 | LANDSCAPE - FINAL | JFEMLING | Approved | Finish all LS and DG prior to final |
| 12/30/2010 | ENGINEERING - FINAL | JFEMLING | Approved | Call for final grading inspection #T09BU00925, and complete all items on punch list prior to final |
| 01/05/2011 | FIRE - ALARM FINAL | DSIWARSKI | Approved | |
| 01/05/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
| 01/06/2011 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
| 01/06/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 02/04/2011 | MECHANICAL - FINAL | LHANLY | Approved | |
| 02/04/2011 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 02/04/2011 | PLUMBING - FINAL | RMYERS | Approved |