Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09CM00849

Parcel: 117050020


Addresses:

400 N 2ND AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T09CM00849

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
12/30/2010 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
10/19/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST SIDE STAIRS AND LANDING-OK TO POUR PROGRESS AREA
09/21/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) NORTH STEM OK
09/10/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) MISSING REBAR
09/10/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EQUIPMENT PAD GL: B/9-10; 5 COLUMN FOOTINGS; GL 10/C-D.5: OK TO POUR PROGRESS AREAS
08/16/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/12/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) E-G.5/12 SCREEN WALL
08/10/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) INTERIOR RAMP WALL FOOTING NORTH WEST CORNER OF GYM
08/09/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REVISED DETAIL 172
08/06/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
LINE 8 A TO B NW CORNER EXT WALL OF RAMP
08/05/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/04/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
08/03/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) NOT READY PER CONTRACTOR
08/02/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
07/30/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) FOOTINGS ARE FLOODED
04/05/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/01/2010 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
01/28/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STEM AT GL F-F.8/0
01/14/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 0-2/6-6.5, B140 AND B141
12/21/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) IN RESPONSE TO RFI #159
12/17/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 7-10/G, K-F 72/12 PENDING LETTER ON RESPONSE TO RFI #157
12/16/2009 EXCAVATION/LAYOUT REBAR & ZON Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) ELECTRIC CONDUIT CANNOT POP THRU FOOTER AS PER DETAIL T-42
11/12/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 5-7/G.5-K
11/10/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
11/09/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) CORRECTION NOT MADE
11/03/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) PLUMBING IN FOOTER, PLUMBING IN CONTROL ? DOOR WAY MISSING REBAR
09/25/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) GL C/3-4, 3/F-G, G/3-3.1, 3.1/24 N OF K.O.
09/24/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 8 CAISSON CAPS AA/5, AA/7, BB/1, CC/1, CC/8, BB/13 AND CC/13
09/22/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 10.0/C.0-D.0
09/08/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 10.11/F
09/04/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) MISSING REBAR
08/28/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL 3.1/J.5-K.0, K0/3.1-5.1, 5.1/K.0-L.0/5.2-6.3, 6.3/L.0-K.0, K.0/6.3-12.0, 12.0/K.0-J.5
08/25/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GL F/1-10, 1/C-F AND C/1-10
08/20/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
G.L. A.4/7, 1-4.1/A-C, C/4.1 - 4.8, 7/A-B, 6.6/A-B, B/7-7.9
08/19/2009 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) MISSING #6 AND ?