Permit: T07CM04093
Permit Details
Apply Date:
10/18/2007
Applicant:
WILLIAM BRAZELTON
Description:
NEW BUILDING DPS
Architects:
- RICE, GEORGE C
Contractors:
- SUMMIT BUILDERS ,
Permit Reviews
Permit Number - T07CM04093
Permit Status: C of o
Permit Description: NEW BUILDING DPS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2008 | POST 3RD PARTY REVIEW | 01/25/2008 | COMPLETED |
| 01/25/2008 | OTHER | 01/25/2008 | COMPLETED |
| 02/12/2008 | POST 3RD PARTY REVIEW | 02/14/2008 | COMPLETED |
| 08/11/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 01/07/2009 | COMPLETED |
| 10/18/2007 | PLANS OK TO SUBMIT - COMM | 10/18/2007 | COMPLETED |
| 10/18/2007 | 3RD PARTY REVIEW-COMMERCIAL | 01/15/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM04093
Permit Status: C of o
Permit Description: NEW BUILDING DPS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/18/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM04093
Permit Description: NEW BUILDING DPS
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/20/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* 1. OK 3/0 20' IN FOOTING 2. OK #4 20 IN FOOTING FOR TELCO |
| 04/15/2008 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/25/2008 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* SOUTH END OF BUILDING ROOF DRAIN TEST OK |
| 09/02/2008 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* BOTTOM OF SOUTH STAIRWELL AND SOUTHWEST ENTRY POUR BACK |
| 09/15/2008 | MECHANICAL - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* UNDERGROUND FROM BLDG. TO COOLING TOWER OK TO BACKFILL |
| 09/16/2008 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* 8 COOLING TOWER COLUMNS, NORTH STEM WALL OK TO POUR GETTING SPECIAL INSPECTION |
| 10/09/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* OK TO WRAP L.P. DUCT SECOND FLOOR |
| 10/21/2008 | BUILDING - FINAL | MHENSON | Approved | INCINERATOR ROOM BEING DONE BY DPS NO INSPECTIONS PERFORMED BY C.O.T (PER SUMMIT BUILDERS) |
| 11/05/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* - CODING TOWERS COPPER DRAIN PIPING FROM SUMP TO BUILDING OK - PIPING PER REDLINES TO BE APPROVED BY CITY OF TUCSON |
| 11/10/2008 | FRAMING | LHANLY | Approved | IVRS - Inspection :* 2ND FLOOR OK -- DO NOT COVER SHAFT WALLS UNTIL FIRE STOP INSPECTED |
| 11/26/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 11/26/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 7' SCREEN SITE WALL AT SW CORNER AND 7' AT SE CORNER WALL S3.4 (45) |
| 12/16/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | |
| 12/16/2008 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/16/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/16/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 12/18/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1. 2ND FLOOR CORRIDOR LID & TOP COURSE OK TO TAPE 2. OK TO HANG CORRIDOR SOFFITS |
| 12/22/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/30/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* 1) SITE WALL TO 4'-8" WEST TECH SPECIAL INSPECTED |
| 01/22/2009 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* 1) NO BOND REQUIRED PER J. SANDERS 2) CONTRACTOR RESPONSIBLE FOR ONLY AUTHORIZED PERSONS TO HAVE ACCESS TO ELECTRIC EQUPMENT |
| 01/23/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 03/07/2009 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* REVIEWED SPECIAL INSPECTIONS AND RESULTING RFI's AND ACCEPTED |
| 03/20/2009 | PLUMBING - MEDICAL GAS/FINAL | RRICH | Approved | IVRS - Inspection :* PARTIAL APPROVAL FOR NOTES BELOW THIS PROJECT IS LABORATORY GASES ONLY NOT FOR HUMAN USE PER ENGINEER LETTER FROM GARY NELSON P.E. 3/18/09 AND TOM HEIDEMAN (DPS FACILITIES MGMT) |
| 03/20/2009 | PLUMBING - MEDICAL GAS/TEST | RRICH | Approved | IVRS - Inspection :* PARTIAL APPROVAL FOR NOTES BELOW THIS PROJECT IS LABORATORY GASES ONLY NOT FOR HUMAN USE PER ENGINEER LETTER FROM GARY NELSON P.E. 3/18/09 AND TOM HEIDEMAN (DPS FACILITIES MGMT) |
| 03/24/2009 | PLUMBING - MD GAS/PRECONST MTG | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/30/2009 | MECHANICAL - HOOD SYSTEMS | MRAMBER | Approved | IVRS - Inspection :* |
| 03/30/2009 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* |
| 04/03/2009 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 04/06/2009 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 04/24/2009 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 04/24/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 05/13/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/14/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 05/15/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 05/15/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 05/22/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 06/03/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 06/12/2009 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/22/2009 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 06/25/2009 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | STATE FIRE MARSHALL FRED DURHAM CALLED ON 06/24/09 LEFT MESSAGE, BUILDING PASSED FINAL INSPECTIONS. |
| 06/25/2009 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | STATE FIRE MARSHALL FRED DURHAM CALLED ON 06/24/09 LEFT MESSAGE, BUILDING PASSED FINAL INSPECTIONS. |
| 06/25/2009 | FIRE - ALARM FINAL | CSCHULTZ | Approved | STATE FIRE MARSHALL FRED DURHAM CALLED ON 06/24/09 LEFT MESSAGE, BUILDING PASSED FINAL INSPECTIONS. |
| 06/25/2009 | FIRE - FINAL | CSCHULTZ | Approved | STATE FIRE MARSHALL FRED DURHAM CALLED ON 06/24/09 LEFT MESSAGE, BUILDING PASSED FINAL INSPECTIONS. |
| 06/26/2009 | PERMIT FINALED | LJACKSON | Approved | |
| 06/26/2009 | MECHANICAL - FINAL | MRAMBER | Approved |