| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/02/2009 | MECHANICAL - ABOVE CEILING | Approved | IVRS - Inspection :* | |
| 03/30/2009 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 03/13/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK FOR CEILING TILES ROOM 253 |
|
| 03/10/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 03/09/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* SECOND FLOOR OK FOR TILES EXCEPT RM. 253 |
|
| 02/27/2009 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* 1. 4" EXH. NOT PROPERLY TERMINATED OR SEALED 2. SUPPLY ELBOW IN CORRIDOR NOT INSULATED |
|
| 02/11/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 02/10/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 02/09/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK FOR TILES 1ST FLOOR MECHANICAL ONLY |
|
| 02/06/2009 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* RM. 114 TRANSFER DUCT BLOCKED LABEL ALL TU-UNITS ELEVATOR CONTROL ROOM COMPLETE CW INSULATION RM. 110 TRANSFER DUCT BLOCKED PROVIDE INSULATION ON LINEARS |
|
| 02/04/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 02/03/2009 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 10/09/2008 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK TO WRAP L.P. DUCT SECOND FLOOR |
|
| 08/28/2008 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* C W S/R PRESSURE TEST COLUMN LINE "11" TO "3" GRID LINE "D" OK |
|
| 08/27/2008 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* H.P INLET TO VAV MUST BE EQUAL DIAMETER OR USE CONICAL REDUCER NOT TO EXCEED 30 DEG. |
|
| 08/01/2008 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* MAIN CORRIDOR SUPPLY DUCTS ABOVE OK TO WRAP RECTANGLE BELOW NEEDS TO BE SEALED |