Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T07CM01074
Permit Details
Apply Date:
03/16/2007
Applicant:
ROBINSON LANCE
Description:
CIRCLE K RETAIL STORE
Contractors:
- THATEN CONSTRUCTION INC
Permit Reviews
Permit Number - T07CM01074
Permit Status: C of o
Permit Description: CIRCLE K RETAIL STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2008 | RESUBMITTAL - SITE ALL | 04/16/2008 | COMPLETED |
| 01/23/2009 | REVISION - - 1ST | 02/04/2009 | COMPLETED |
| 02/01/2008 | POST 3RD PARTY REVIEW | 04/16/2008 | COMPLETED |
| 03/16/2007 | PLANS OK TO SUBMIT - SITE | 03/20/2007 | COMPLETED |
| 03/20/2007 | SITE | 05/22/2007 | COMPLETED |
| 04/08/2009 | REVISION - - 2ND | 04/09/2009 | COMPLETED |
| 04/16/2008 | RESUBMITTAL - SITE | 05/12/2008 | COMPLETED |
| 05/12/2008 | RESUBMITTAL - SITE | 06/27/2008 | COMPLETED |
| 06/14/2007 | RESUBMITTAL - SITE ALL | 08/02/2007 | COMPLETED |
| 06/27/2008 | RESUBMITTAL - SITE | 11/24/2008 | COMPLETED |
| 08/21/2007 | RESUBMITTAL - SITE ALL | 10/19/2007 | COMPLETED |
| 09/11/2008 | RESUBMITTAL | 11/03/2008 | COMPLETED |
| 10/10/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 10/19/2007 | COMPLETED |
| 10/19/2007 | 3RD PARTY REVIEW-COMMERCIAL | 02/01/2008 | COMPLETED |
| 11/03/2008 | RESUBMITTAL | 11/24/2008 | COMPLETED |
| 11/20/2007 | RESUBMITTAL - SITE ALL | 01/23/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01074
Permit Status: C of o
Permit Description: CIRCLE K RETAIL STORE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/16/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM01074
Permit Description: CIRCLE K RETAIL STORE
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2008 | TEP CLEARANCE - PM | BFLORES | Approved | TMPP PER D.SANTA CRUZ (TEMP POLE) |
| 12/15/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* OK RELOCATED TEMP POLE SERVICE |
| 12/19/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* OK 4" PVC TO TEP X-FORMER FROM POLE |
| 12/30/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* 1) ROUGH SOIL TEST OK 2) CALL BACK FOR PRE-SLAB UNDER ROUGH SOIL |
| 12/30/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/30/2009 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/24/2009 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* |
| 02/26/2009 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* |
| 03/02/2009 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/06/2009 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 03/24/2009 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 03/30/2009 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/01/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2009 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 04/02/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/03/2009 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/13/2009 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* PARTIALS BY GLENN, JIM |
| 04/13/2009 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* RFI FOR MONO POUR |
| 04/13/2009 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 04/14/2009 | FRAMING | MHENSON | Approved | IVRS - Inspection :* 1) RFI DATED 4/13/09 |
| 04/14/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 04/17/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/17/2009 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/20/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 04/21/2009 | FIRE - HYDRANTS | DRAMIREZ | Approved | |
| 04/21/2009 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 04/21/2009 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* |
| 04/21/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 04/23/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* 1) OK FINAL |
| 04/23/2009 | LANDSCAPE - FINAL | DRAMIREZ | Approved | |
| 04/23/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - TEMPORARY SERVICE | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/23/2009 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/24/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL TESTED DUCT SMOKE DETECTORS AIR BALANCE OK |
| 04/24/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 04/24/2009 | FIRE - FINAL | DRAMIREZ | Approved | |
| 04/27/2009 | ENGINEERING - FINAL | MAVERY | Approved | Contractor provided letter from engineer. |
| 05/05/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* NEEDS PLUMBING FINAL |
| 05/05/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/28/2009 | RIGHT OF WAY - FINAL | THARVISON | Approved | APPROVED |
| 07/29/2009 | PERMIT FINALED | LJACKSON | Approved |