Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2009 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 05/01/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 04/24/2009 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* 1. PROVIDE SUPPORT ON DRAINS AND AIR GAP 2. PROVIDE CLEAN WATER REPORT |
|
| 04/23/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) COMPLETE DRAINS 2) PAINT VENTS ON ROOF 3) PROVIDE CERTS FOR BACKFLOWS 4) PROVIDE TEST ON MOP SINK 5) PROVIDE STAMPED LETTER FROM ENGINEER ON FIXTURE CHANGES 6) PROVIDE APPROVED CLEANOUT PLUGS AND SCREWS 7) PROVIDE CHLORINATION REPORT 8) LIST MAY NOT BE COMPLETE |
|
| 04/22/2009 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* VENT OFF FLOW CONTROL IN WALLS OK |
|
| 04/21/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* COMPLETE ALL WORK BEFORE CALLING FOR FINAL INSPECTION |
|
| 04/20/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* COMPLETE ALL WORK BEFORE CALLING FOR FINAL |