Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL OTHER
Address:
945 E OHIO ST
Apply Date:
12/12/2006
Applicant:
MICHAEL BECHERER
Description:
TI:OFFICE/WAREHOUSE
Architects:
  • MICKELBERG, PAUL DAVID
Contractors:
  • LLOYD CONSTRUCTION COMPANY INC ,

Permit Reviews

Permit Number - T06CM06275
Permit Status: C of o
Permit Description: TI:OFFICE/WAREHOUSE
Start Date Submittal Complete Date Status  
02/20/2007 RESUBMITTAL - SITE 03/23/2007 COMPLETED Review Details
03/23/2007 RESUBMITTAL - SITE ALL 04/19/2007 COMPLETED Review Details
05/01/2007 RESUBMITTAL - SITE ALL 05/10/2007 COMPLETED Review Details
05/07/2007 POST 3RD PARTY REVIEW 05/14/2007 COMPLETED Review Details
12/12/2006 PLANS OK TO SUBMIT - SITE 12/12/2006 COMPLETED Review Details
12/12/2006 SITE 02/16/2007 COMPLETED Review Details
12/15/2006 PLANS OK TO SUBMIT - 3RD PARTY 12/15/2006 COMPLETED Review Details
12/15/2006 3RD PARTY REVIEW-COMMERCIAL TI 05/07/2007 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM06275
Permit Status: C of o
Permit Description: TI:OFFICE/WAREHOUSE
Total Outstanding Activity Conditions - 1
Date Name
12/12/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM06275
Permit Description: TI:OFFICE/WAREHOUSE
Total Completed Inspections - 40
Date Description Inspector Results Comments
07/25/2007 ELECTRIC - UFER DSANTACR Approved - OK ELECTRICAL ROOM, GENERATOR AREA GROUNDING & UG
FEEDER CONDUITS, 3/0 GROUND TO COLUMN "A5"
- OK FLOOR BOXES ROOM #133 & #106
10/01/2007 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection :*
10/17/2007 PLUMBING - ROOF DRAINS RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - YARD WTR LINE/TEST RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - PRE SLAB RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - ROUGH, SOIL RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - GAS PRESSURE TEST RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - ABOVE CEILING RLEDONNE Approved IVRS - Inspection :*
11/09/2007 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
11/13/2007 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) 3 AT EXTERIOR CANOPIES-OK TO DRY IN
11/20/2007 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection :*
RAMP @ NE CORNER
11/21/2007 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
OK WALLS
11/26/2007 FRAMING LHANLY Approved IVRS - Inspection :*
11/26/2007 STUCCO MESH LHANLY Approved IVRS - Inspection :*
12/04/2007 EXCAVATION/LAYOUT REBAR & ZON MHENSON Approved IVRS - Inspection :*
PARTIAL PER SPECIAL INSPECTION
EAST ELEVATION SEE WALL
12/18/2007 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
OK TO INSTALL CEILING TILES FOR MECHANICAL
OK TO ROCK LIDS FOR MECHANICAL
12/20/2007 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*
ALL ROCK DONE EXCEPT LIDS & SOFFIT @ BULD DROP OFF
WET DROP OFF
CORRIDOR 146
12/20/2007 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection :*
TOP EAST 8' N.W
12/21/2007 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
1) GAS CONNECTIONS TO UNITS ON ROOF OK
12/21/2007 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
12/31/2007 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
UPPER LEVEL ALL ROOMS
OK TO TILE ACOUSTIC CEILING WHEN OTHER TRADES OK
12/31/2007 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
OK RAISED OFFICE AREA EXCEPT ROOM 200
01/28/2008 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED FOR #M1 PER D. SANTACRUZ
03/11/2008 OUTDOOR LIGHTING FINAL DSANTACR Approved IVRS - Inspection :*
03/11/2008 ELECTRIC - OUTDOOR LIGHTING DSANTACR Approved IVRS - Inspection :*
03/11/2008 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
03/20/2008 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
ALL DUCT SMOKE DETECTORS OK
SEE BLDG. INSPECTOR FOR C.O
04/04/2008 PLUMBING - GAS PRESS TEST FNL RLEDONNE Approved
04/05/2008 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
04/28/2008 U VALUE FOR WINDOW LHANLY Approved
05/01/2008 FIRE - ALARM FINAL LTHOMAS Approved
05/01/2008 FIRE SPKLR - FINAL LTHOMAS Approved
05/12/2008 RIGHT OF WAY - FINAL MOTERO Approved PER EMAIL
05/12/2008 LANDSCAPE - FINAL ACONNOR Approved
05/12/2008 FIRE - FINAL LTHOMAS Approved
05/12/2008 SIGN - FINAL JYBARRA Approved
05/19/2008 ENGINEERING - FINAL MAVERY Approved Contractor addressed punch list.
05/22/2008 BUILDING - FINAL LHANLY Approved IVRS - Inspection :*
1) WAITING FOR E-MAIL ONLY
05/27/2008 PERMIT FINALED LJACKSON Approved
05/27/2008 ELECTRIC - FINAL DSANTACR Approved