Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2007 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 09/18/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SUMP PIPING PVC 3' TRACER WIRE AND TEST OK TO SUMP ONLY |
|
| 09/14/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. SAND & OIL SEPARATOR AT NORTHEAST END OF BUILDING OK 2. ABOVE CEILING NOTE FROM 9/12/07 |
|
| 07/25/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1. #102 & #103 RESTROOM AND FLOOR SINK PRE-SLAB OK |
|
| 07/05/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* NEW 4" MAIN ON EAST SIDE OF BUILDING TEST OK |
|
| 06/28/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* NEW 4" MAIN ON WEST SIDE PER RED DRAWING |
|
| 06/21/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* NEW 4" MAIN PVC J TO E AND #4 TO #5 TEST OK |
|
| 06/19/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* TDI'S, BDI'S FLOOR DRAIN FROM #4 TO #5 AND H TO N TEST OK |
|
| 06/12/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 4" BUILDING DRAIN IS REPLACED FROM CAST IRON TO PVC SCH 40 FROM LINE H THRU N, 4 THRU 5 WATER TEST OK WILL NEED TO SEE CONTINUATION |
|
| 06/06/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* H LINE THRU LINE M & #4 THRU #5 ALL UNDERGROUND TIE INTO (E) 4" CALL BACK FOR PIPING TO SAND & OIL INTERCEPTOR |
|
| 06/01/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* LINE A TO G & #3 TO #5 TEST OK |
|
| 05/29/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* EASTSIDE OF OFFICE ROUGH SOIL TEST OK LINE #5 TO #8 & A TO E |
|
| 05/25/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* ADD FLOOR DRAIN TO ROUGH-SOIL #221 CLEAN UP ROOM |