Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
08/31/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI: DENTAL OFFICE- FIRST TENANT IN SHELL
Contractors:
  • CAYLOR CONSTRUCTION COMPANY , RO

Permit Reviews

Permit Number - T06CM04873
Permit Status: C of o
Permit Description: TI: DENTAL OFFICE- FIRST TENANT IN SHELL
Start Date Submittal Complete Date Status  
04/05/2007 POST 3RD PARTY REVIEW 04/06/2007 COMPLETED Review Details
04/09/2007 POST 3RD PARTY REVIEW 04/10/2007 COMPLETED Review Details
08/31/2006 PLANS OK TO SUBMIT - 3RD PARTY 08/31/2006 COMPLETED Review Details
08/31/2006 3RD PARTY REVIEW-COMMERCIAL TI 04/05/2007 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM04873
Permit Status: C of o
Permit Description: TI: DENTAL OFFICE- FIRST TENANT IN SHELL
Total Outstanding Activity Conditions - 1
Date Name
08/31/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM04873
Permit Description: TI: DENTAL OFFICE- FIRST TENANT IN SHELL
Total Completed Inspections - 32
Date Description Inspector Results Comments
08/14/2007 ELECTRIC - TEMPORARY SERVICE RJIROUDE Approved IVRS - Inspection :*
1) TEMP SERVICE FOR CONSTRUCTION POWER
08/15/2007 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR #101 PER R. JIROUDEK
08/17/2007 ELECTRIC - UFER RJIROUDE Approved IVRS - Inspection :*
1. OK 3/0 COPPER TO REBAR IN FOOTING GEC
2. OK 3/0 COPPER TO REBAR IN FOOTING WATER BOND
3. OK 3/0 COPPER TO REBAR IN FOOTING SPRINKLER BOND
4. OK #6 COPPER TO REBAR IN FOOTING FOR TELEPHONE
08/21/2007 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
09/20/2007 ELECTRIC - UNDERGROUND RJIROUDE Approved IVRS - Inspection :*
1) OK 3-2 1/2" PVC FROM SES TO PANEL LOCATIONS
2) OK 3/4" RIGID CONDUIT UNDER SLAB FOR POWER
3) OK 2" PVC UNDER SLAB FOR TELEPHONE/DATA
09/26/2007 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
TI @ SOUTH END NOT TO BE POURED UNDER SHELL PERMIT
11/27/2007 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
1) DWV WATER TEST THRU ROOF AND WATER PIPING OK
2) CALL IN FOR CLOSET FLANGE INSPECTION
11/27/2007 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
11/28/2007 FRAMING GDABBS Approved IVRS - Inspection :*
12/11/2007 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
BRAZING OF NITROUS OXIDE, OXYGEN, COMPLETED AIR
12/11/2007 PLUMBING - MEDICAL GAS/FINAL RRICH Approved IVRS - Inspection :*
12/19/2007 PLUMBING - MEDICAL GAS/TEST RRICH Approved IVRS - Inspection :*
TESTING IN PLACE FOR ALL MED GAS PIPING
NEED 3RD PARTY VERIFICATION SIGNED OFF ON PERMIT CARD
NEED COMPLETION OF LABELING
12/27/2007 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
1) OK WALLS
02/20/2008 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
02/20/2008 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
02/26/2008 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
OK FOR CEILING TILES
02/26/2008 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
CORRECTION OF NUMBER 1 FROM PREVIOUS INSPECTION COMPLETED
03/12/2008 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
03/12/2008 NPPO - FINAL ACONNOR Approved
03/12/2008 LANDSCAPE - FINAL ACONNOR Approved
03/12/2008 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
03/14/2008 FIRE SPKLR - FINAL LTHOMAS Approved
03/14/2008 FIRE - FINAL LTHOMAS Approved
03/26/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
TESTED DUCT SMOKE DETECTORS
OK FOR FINAL
03/26/2008 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
03/26/2008 STUCCO MESH GDABBS Approved IVRS - Inspection :*
03/26/2008 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
03/27/2008 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
04/02/2008 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
04/23/2008 ENGINEERING - FINAL NKALAHAR Approved CP-COMPLETE ALL ASPHALT PATCHES

CP-CLEAN UP WASH OUT AND CONSTRUCTION DEBRIS S OF SCREEN WALL

CP*-ADDRESS ADA ISSUES-APPROVED REVISION MUST BE READY TO BUILD BEFORE TEMP C OF O. THIS INCLUDES H/C PARKING STALLS TOO STEEP ON N SIDE FO BLDG AND ADA ACCESSIBLE ROUTE FROM ROW TO 8265.

CP-INSTALL BIKE LOCKERS PER PLAN (DEV PLAN)--2 BIKE LOCKERS INSTALLED NE CORNER OF BLDG TOTAL OF 4 EACH CLASS 1 + 2 INSTALLED ON SITE

CP*REVISED DEVELOPMENT PLAN ON SITE-NO REVISED GRADING PLAN
04/23/2008 ENGINEERING - FINAL NKALAHAR Approved
04/23/2008 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*

Documents

File Name Document Type  
C OF O_04-23-2008.TIF CERT OF OCC VIEW
TEMP C OF O_03-27-2008.TIF CERT OF OCC VIEW
None CONSTRPLANS VIEW
PROVISIONAL_COFO.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW