Permit: T05CM04691
Permit Details
Apply Date:
09/13/2005
Applicant:
M3 ENGINEERING & TECHNOLOGY
Description:
NEW MANUFACTURING FACILITY
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Outstanding Activity Conditions
Permit Number - T05CM04691
Permit Status: C of o
Permit Description: NEW MANUFACTURING FACILITY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/13/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM04691
Permit Description: NEW MANUFACTURING FACILITY
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/30/2006 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 06/27/2006 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* 1) OK GROUNDING AT SES, MCC, X-FORMERS IN ELECTRIC ROOM 2) GCI MAIN TESTED AT FACTORY, PLEASE FIELD TEST AND SUBMIT RESULTS TO INSPECTOR |
| 06/28/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 06/30/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | Need As-Built to reflect reality |
| 07/16/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* 1. EAST RATED WALL -- FIRE DAMPERS W/WRAPPED OPENINGS 2. OK TO WRAP/INSUL. PROGRESSING |
| 08/17/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 08/17/2006 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* |
| 08/17/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
| 08/18/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 08/22/2006 | FIRE - HYDRANTS | LTHOMAS | Approved | |
| 08/31/2006 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/31/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 10/31/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 10/31/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 10/31/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 10/31/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/31/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 11/01/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 11/02/2006 | BUILDING - PROGRESS | LHANLY | Approved | |
| 11/02/2006 | U VALUE FOR WINDOW | LHANLY | Approved | |
| 11/02/2006 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
| 11/02/2006 | BUILDING PRE-SLAB | LHANLY | Approved | |
| 11/02/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
| 11/02/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 11/03/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* SITE SEWER FROM PUBLIC MANHOLE 21' OF DUCTILE IRON INSTALLED. |
| 11/09/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* 1. NEED TO PROVIDE FIRE SEALANT NEXT TO BEAM BETWEEN COMPRESSOR ROOM & BOILER ROOM. 2. H.C PARKING TO COMPLY WITH ANSI FOR SLOPE 3. REPORTS. NOTE: EXIT SIGN AT DOOR 113A IN COMPLIANCE (2) REMOVED BOILER (6) GRADE BLD. PERIMETER (3) ACCESSIBLE SIGNAGE (4) TIES FOR ROBOT CRANE (8) |
| 11/09/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 11/09/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
| 11/09/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
| 11/13/2006 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | |
| 11/13/2006 | FRAMING | LHANLY | Approved | |
| 11/13/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/16/2006 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* VACUUM TEST ON MANHOLE #3 APPROVED TEST OK |
| 11/16/2006 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/17/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
| 11/17/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 11/17/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | OK for C of O |
| 12/12/2006 | ENGINEERING - FINAL | MAVERY | Approved | Contractor completed outstanding items. |
| 01/08/2007 | PERMIT FINALED | LJACKSON | Approved |