Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T05CM04691

Parcel: 130010050


Addresses:

2965 E FAIRLAND SV


Inspection Status: Approved

Inspection History: STEM WALL/RETAINING WALL

Permit Number - T05CM04691

Inspection Description - STEM WALL/RETAINING WALL

Inspection Status - Approved

Date Description Inspector Results Comments
11/09/2006 STEM WALL/RETAINING WALL Approved IVRS - Inspection :*
11/02/2006 STEM WALL/RETAINING WALL Partial Approval PROVIDE CONC. BREAKS FOR BINS
10/02/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
CONCRETE WALL
0'-50' N OF GL A/30.7-31
0' 17' A.F.F.E
DETAILS IN COMPLIANCE WITH APP. PLANS
09/12/2006 STEM WALL/RETAINING WALL Not ready for Inspection
09/12/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
GRIDLINE @ A/30.7-31.00
09/08/2006 STEM WALL/RETAINING WALL Cancelled BY G.C. RICHARD 9/7/06 @ 9:00 AM
09/05/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
GL (GRIDLINE) A-31 20' EAST
A-31.3 45' EAST TO 8.9 - 12' A.F.F.E
A.8-31.1 44' OF A.1-A.8
08/31/2006 STEM WALL/RETAINING WALL Cancelled CANCELLED BY RICHARD D.D.C
08/30/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PARTIAL @ ROBOT CRANE RAIL 20' FROM GRIDLINE 1 DETAIL 10/SB501
08/29/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
NOTE: GRIDLINE A.1/31.0
A.1-A.8/31.0
DETAILS 1/7 SB502/SB505
08/25/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
NOTE: RAIL FOUNDATIONS DETAIL 10/SB501
RETAINING WALL DETAIL 7/SB505
1/SB502
08/24/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PARTIAL @ ROBOT CRANE FOUNDATION 72' PLUS 80' TOTAL LONG.
GRIDLINE 22' N OF (A) DETAIL 10/SB101 SHEET SB501
08/23/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PARTIAL @ ROBOT CRANE 72' LONG
GRIDLINE 22'N OF A
DETAIL 10/SB101 SHEET SB501
08/22/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PARTIAL @ DETAIL 13/SB503 GRIDLINE 30 -31 REVISION 1
08/17/2006 STEM WALL/RETAINING WALL Not ready for Inspection IVRS - Inspection :*
CANCELLED
08/07/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
BINS @ Y2 TO TOP (EXCEPT OVER SLAB)
07/24/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
150' OF NORTH GANTRY FOOTING
07/14/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
1/3 AREA LINE 30.8 ANGLED WALL TO +8' AFF (WILL BE LOADING SLAB LEVEL)
06/23/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
1. STAIR AREA A-A.5/13 OK TO 0' (GRADE)
2. STORAGE BUNKERS Y3 AREA OK TO +8' (AFG)
06/21/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
BATCH PLANT AREA FLOOR 30 THRU 31 8/SB502 & 11/SB505 B.F.F 6'0"
STEM WALL FOR BATCH PLANT DETAILS 9/SB505, 13/SB301
06/16/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
A THRU B 24.3 COLUMNS
CRANE RAILFOOTING 10/SB101
18 H FROM A
06/15/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
3 FOOTINGS ON B2 1/SB505 7/SB504
06/14/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
BATCH PLANT AREA SECTION RET. WALL (5)/COLUMNS ON 43 ON EACH SIDE
COLUMNS ON 43 ON EACH SIDE.
06/05/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
LONG WALLS 2 SLABS @ STAIR LANDING SFS02 SHEET
6 & 7 SB104
SUMP/SHEET SB503
DETAIL 9 SB103
06/01/2006 STEM WALL/RETAINING WALL Not ready for Inspection IVRS - Inspection :*
FINISH STEEL.
05/19/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
SETTLING PONDS 1-4
05/16/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
TO BOTTOM OF CORBEL @ PIT
05/09/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PIER CAPS LINE B OK
05/08/2006 STEM WALL/RETAINING WALL Not ready for Inspection IVRS - Inspection :*
NO FORMS OR STEEL IN PLACE FOR PRS
05/04/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
04/28/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
BATCH PLANT SUMP 3RD LIFT CIP WALL OK
04/26/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
2ND LIFT TO SUB Y3/A.2 OUT OF BATCH PLANT
04/10/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
BATCH PLAN AREA FOUNDATION (1ST LIFT ABOVE SUMP)
03/30/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
TRENCH DRAIN WALLS/B/16-25
03/23/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
SUMP PIT WALLS OK (9/SB5O2)
03/15/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
03/13/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
1) NORTH SUMP TUNNEL ENCLOSURE OF TO CLOSE AND POUR
2) SOUTH SIDE OF TRENCH DRAIN AT B/1-3-TIGHTEN UP ANGLE IRON OK TO CLOSE AND PLACE
03/08/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
SOUTH SUMP TUNNEL ENCLOSURE OK
03/01/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
02/27/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
PIER COLS @ C/14, 15 OK
02/23/2006 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*