Permit: T05CM04691

Parcel: 130010050


Addresses:

2965 E FAIRLAND SV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T05CM04691

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
11/02/2006 EXCAVATION/LAYOUT REBAR & ZON Approved
08/22/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PARTIAL @ RETAINING WALL 52'N/0'-50' E OF 6.L A/31 DETAIL 1/SB103
07/19/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
RETAIN FOOTING (216') @ PROP LINE OK
05/04/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F1 AND F3 FOOTINGS AREA O-L/28-31
04/24/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
OFFICES SLAB & TOEDOWNS (LINES 20-29/C-D & 29-31/B.6-D)
04/06/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PERMETER FOOTINGS TO LINE 13/GANTRY CRANE FOOTING NOT READY
04/05/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F2 FOOTINGS
03/30/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. TRENCH DRAIN B/13-16
2. SLAB TO WALL @ BUNKER PP 58104 AND 6/58504 AND 98/S5502 @ 30.1/A.1
03/24/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F2 FOOTINGS LINE D/20-30 OK TO PLACE
F4 FOOTING D/31 OK TO PLACE
03/23/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EXCAVATIONS FOR F2 FOOTINGS LINE D FROM 14.3-30 OK BUT LACKING Z BARS
03/20/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SUMP PIT BASE REF SB104 & 9/SB502
03/15/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
BOTTOM OF TRENCH DRAIN LINE B/16-25
03/13/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/10/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STRESS BED @ 1/2 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS CLEARANCE CORRECTIONS NOTED WITH SUPERINTENDENT.
03/08/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SOUTH SUMP TUNNEL ENCLOSURE @ 14.5
03/07/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F1 FOOTINGS @ B&C/15 ; TRENCH DRAIN @ B/1-B
03/03/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CATCH BASINS @ LINE 15 OK; STRESS BED AT Y1; AND MORE PIER CAPS.
03/01/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) F1 FOOTINGS COMPLETE FROM 1-27 LINES B AND C ALSO 6 PIER CAPS
02/27/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
STRESS BED @ B-C/24-25 OK TO PLACE WHEN SP. INSP. CONFIRMS MAT HAS BEEN PLACED ON DOBIE PROPERTY.
PIER ? AT B1; F1 FOOTINGS AT B-2, 3 AND 4; F1 FOOTINGS AT C2.3 PIER CORP AT B-5, 6, 7, 8, 9, 10 AND 11; PIER COLUMNS AT B 14 AND 15
02/23/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F1 FOOTINGS LINE B/17-23; LIGHT BOXES LINE C/17-23
1. DETAIL 8 SB505 COLUMN CASES REQUIRE HOOKS TO BE STAGGERED - OK TO CLOSE FORMS FOR PIERS WHEN SPECIAL INSP. CONFIRMS
02/15/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STRESS BED 2.5-3.5/B-C OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS CONSTRUCTION JOINT AT 3.5
02/14/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*LINE C /5-12 F1 FOOTINGS OK TO PLACE