Plan: S03-014
Plan Details
Apply Date:
06/19/2003
Applicant:
TSANG, ANTONY C
Description:
SUBC
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/23/2005 | ASSURANCE - DOT TRAFFIC | TSTOCKET | Approved | |
| 08/03/2006 | ASSURANCE - UTILITY SERVICES | LHenandez | Approved | Plan No. 2-085-161-2003 Approved |
| 12/13/2007 | ASSURANCE - DSD | DROBERTS | Approved | THE SITE WAS CHECKED FOR THE FULL RELEAS OF THE ASSURANCES, IT IS NOT READY AT THIS TIME. THE FOLLOWING LOTS HAVE BEEN COMPLETED AT THIS TIME: 2-5, AND 19-26. LOT #6 IS CURRENTLY UNDER CONSTRUCTION, LOTS 1, 7-16, 27-31 ARE UNDEVELOPED. ALL LOT RELEASES ABOVE THE 75% WILL REQUIRE A COMPLETION BOND FOR ALL REMAINING ASSURABLE ITEMS. PONDING WATER HAS BEEN NOTED THROUGHOUT THE SITE AT THE FOLLOWING LOCATIONS: INTERSECTION OF MISSIONDALE RD. AND DUOBA LANE, WEST OF LOTS 9 & 31 ADJACENT TO HANDICAP ACCESS RAMPS. WEST OF LOTS 27 & 28, AND IN THE INTERSECTION OF DUOBA LANE AND RADEC LANE. THE BASIN DOES NOT FUNCTION AS SPECIFIED IN THE PIMA COUNTY/CITY OF TUCSON RETENTION DETENTION MANUAL, IT DOES NOT DRAIN WITHIN THE REQUIRED TIME RESTRAINTS. |
| 02/17/2009 | ASSURANCE - PC WASTEWATER | RMONTOYA | Approved | SEE SIRE |
| 11/04/2019 | ASSURANCE - DOT PERMITS & CODE | RLEIGH | Approved |
Plan Reviews
Plan Number - S03-014
Plan Status: Final
Plan Description: SUBC
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2004 | ASSURANCES | 03/05/2004 | COMPLETED |
| 02/10/2004 | RESUBMITTAL - FINAL PLAT REVIEW | 02/26/2004 | COMPLETED |
| 03/05/2004 | RESUBMITTAL - FINAL PLAT REVIEW | 03/19/2004 | COMPLETED |
| 03/05/2004 | ASSURANCES | 04/01/2004 | COMPLETED |
| 03/31/2004 | FINAL PLAT PACKAGE | 04/02/2004 | COMPLETED |
| 04/01/2004 | ASSURANCES | 04/30/2004 | COMPLETED |
| 04/05/2004 | FINAL PLAT PACKAGE | 04/30/2004 | COMPLETED |
| 06/19/2003 | TENTATIVE PLAT REVIEW | 07/24/2003 | COMPLETED |
| 08/19/2003 | RESUBMITTAL - TENTATIVE PLAT REVIEW | 09/05/2003 | COMPLETED |
| 09/25/2003 | RESUBMITTAL - TENTATIVE PLAT REVIEW | 10/09/2003 | COMPLETED |
| 11/21/2003 | FINAL PLAT REVIEW | 12/18/2003 | COMPLETED |