Plan: S03-014

Parcel: 138210010


Addresses:

131 W ELVIRA RD

Inspection Status: Approved

Inspection History: ASSURANCE - DSD

Date Description Inspector Results Comments
11/04/2019 ASSURANCE - DSD Approved
09/26/2011 ASSURANCE - DSD Partial Approval MR. STEVE RUSSO CALLED AND LEFT ME A MESSAGE ON MY PHONE FRIDAY AND ASKED THAT I CONTACT GREG SASSY TO DISCUSS WHAT IS NEEDED TO SATISFY THE ASSURANCES ON THIS SITE. GREG SASSE AND I DISCUSSED THE CURRENT ISSUES FOR THIS SITE THIS MORNING AND THAT THERE IS ALOT OF WORK THAT NEEDS TO BE COMPLETED ON THIS SITE PRIOR TO US RELEASING THE COMPLETION BOND THAT HAS BEEN PLACED. HE WILL RELAY THIS INFORMATION TO THE OWNERS OF THE SITE SO THAT THEY CAN PLAN WHAT WORK WILL NEED TO BE SCHEDULED AND COMPLETED PRIOR TO US CONSIDERING A FULL RELEASE FOR THIS SITE.
09/22/2011 ASSURANCE - DSD Partial Approval WENT OUT TO THE SITE TO SEE WHAT TYPE OF PROGRESS HAS HAPPENED SINCE MY LAST INSPECTION OF THE SITE. THE DEVELOPER ASKED FOR THE FULL RELEASE OF THE SITE SO THAT IT CAN BE SOLD. THIS IS NOT POSSIBLE AT THIS TIME DUE TO THE QUANTITY AND TYPE OF WORK THAT IS STILL NEEDED ON THIS SITE. I TRIED TO CONTACT BOB RUSSO WITH SOUTHERN ARIZONA LAND TRUST AT 529-1515 AND ADVISE HIM OF THE REMAINING ISSUES BUT HAVE BEEN UNABLE TO REACH HIM. I LEFT HIM A MESSAGE FOR HIM TO CALL ME AT A TIME THAT IS CONVENIENT FOR HIM SO THAT WE CAN DISCUSS WHAT ARE THE OPTIONS FOR THIS SITE.
09/17/2008 ASSURANCE - DSD Partial Approval GERALD RETURNED THE CHANGED ESTIMATE FOR REVIEW, IT APPEARS TO BE ACCEPTABLE AT THIS TIME. GERALD WILL BE RESUBMITTING THIS COST ANALYSIS TO TAMARA HAUSER FOR THE PLACEMENT OF THE COMPLETION BOND PENDING APPROVAL BY MATTHEW FLICK.
09/16/2008 ASSURANCE - DSD Partial Approval RECEIVED THE SPREADSHEET FOR DESERT VISTA AND HAVE REJECTED IT AT THIS TIME FOR INCORRECT FIGURES. I HAVE CORRECTED THE QUANTITIES AND HAVE RETURNED IT BACK TO GERALD TUGGLE FOR THE CORRECTIVE MEASURES FROM HIS DEPARTMENT.
08/28/2008 ASSURANCE - DSD Partial Approval MET ONSITE WITH THE DEVELOPER ABOUT THE RELEASE OF ALL LOTS FOR THIS SUBDIVISION. MR. TUGGLE WILL SUBMIT A COST ESTIMATE FOR THE PLACEMENT OF A COMPLETION BOND FOR THIS AREA. AFTER THE ESTIMATE IS CHECKED FOR THE DESIRED QUANTITIES I WILL DIRECT THE DEVELOPER TO SUBMIT IT TO TAMARA HAUSER.
08/27/2008 ASSURANCE - DSD Cancelled IVRS - AP canceled
08/19/2008 ASSURANCE - DSD Cancelled IVRS - AP canceled
08/18/2008 ASSURANCE - DSD Cancelled IVRS - AP canceled
06/10/2008 ASSURANCE - DSD Partial Approval THE COMMON AREAS STILL NEED TO BE COMPLETED AND THE DETENTION RETENTION REPAIRS STILL NEED TO BE MADE PRIOR TO THE FINAL REQUEST FOR THE FULL RELEASE OF THE ASSURANCES. AN APPROVAL OF THE INSPECTION WAS NOTED ON 1/30/2008, BUT THIS WAS ONLY FOR THE COMPLETION BOND ACCEPTANCE. THIS SITE WILL BE REINSPECTED PRIOR TO RELEASING ALL OF THE REMAINING BONDS FOR THE SITE, THIS WILL INCLUDE THE COMPLETION AND THE GRADING RESEEDING.
01/30/2008 ASSURANCE - DSD Approved I RECEIVED A COPY OF THE ESTIMATE RESUBMITTAL AND HAVE VERIFIED THAT THE BOND AMOUNT OF $151,450.00 PLUS THE $5,000.00 MOBILIZATION AND 15% CONTINGENCY IS ENOUGHT TO COVER THE REMAINING ASSURABLE ITEMS FOR THE ENGINEERING SECTION.
THERE HAVE BEEN PROBLEMS IN THE PAST WITH THE DRAINAGE WATER IN AND AROUND THE PROJECT AND THE WAY IN WHICH IT DRAINS. THIS WILL BE RECHECKED IN THE FUTURE TO ENSURE THAT THE WATER IS LEAVING THE SITE WITHIN THE PRESCRIBED TIME FRAMES AS MANDATED BY THE PIMA COUNTY / CITY OF TUCSON RETENTION/DETENTION MANUAL. ALL DRAINAGE FACILITIES AT THAT TIME WILL NEED TO BE COMPLETED AND ACCEPTED BY THE ENGINEERING INSPECTOR FOR THIS SITE.
01/28/2008 ASSURANCE - DSD Partial Approval CHRIS CONTACTED ME THIS MORNING TO GO OVER THE ITEMS THAT WERE DISCUSSED ON FRIDAY. I REMINDED HIM THAT ALL OF THE ITEMS WERE WITHIN REASON EXCEPT THE SIDEWALK AND DRIVEWAY QUANTITIES. THE SIDEWALK AND DRIVEWAY QUANTITIES ONLY NEED TO REFLECT THE ACTUAL AMOUNTS THAT HAVE BEEN REQUIRED BY THE APPROVED PLANS. HE ADVISED ME THAT HE WILL BE LEAVING THE SIDEWALK QUANTITIES AS THEY ARE(HIGH) AND WILL REFLECT THE NEW DRIVEWAY CALCULATIONS. THIS BOND ESTIMATE WILL BE SENT TO ME LATER ON TODAY AND WILL BE LOOKED AT ONCE IT HAS BEEN RECEIVED.
01/25/2008 ASSURANCE - DSD Partial Approval I PLACED A CALL TO CHRIS PAPOUTSIS WITH PAPOUTSIS GENERAL CONTRACTING AT 688-5151 AND LEFT A MESSAGE FOR HIM TO CALL ME IN REGARDS TO DESERT VISTAS BOND CALCULATIONS. CHRIS CONTACTED ME THIS AFTERNOON, WE DISCUSSED THE CLARIFICATION OF SOME OF THE LINE ITEMS THAT THEY HAVE PLACED IN THEIR COMPLETION BOND. HE WAS ADVISED THAT THE BOND AMOUNT WAS SHORT BECAUSE THEY HAD NOT INCLUDED ENOUGH MONEY TO COVER THE MISSING DRIVEWAYS. HE WILL BE ADJUSTING THE AMOUNT TO COVER THE MISSING 16 DRIVEWAYS THAT WERE NOT INCLUDED PREVIOUSLY. ONCE THIS INFORMATION IS FAXED TO OUR OFFICE I WILL RE-INSPECT THE SITE FOR THE VERIFIACATION OF ALL THESE ITEMS.
01/24/2008 ASSURANCE - DSD Partial Approval THE SITE HAS BEEN CHECKED FOR THE FINAL RELEASE OF THE ASSURANCES AND HAS BEEN FOUND TO BE INCOMPLETE AT THIS TIME FOR THE FOLLOWING REASON. THE ATTACHED COMPLETION BOND DOES NOT COVER ALL OF THE ITEMS THAT STILL REMAIN TO BE CONSTRUCTED AT THIS TIME. THE DEVELOPER HAS BEEN ASKED TO PROVIDE THIS OFFICE WITH ADDITIONAL DOCUMENTATION FOR THE MISSING QUANTITIES OF DRIVEWAYS CURRENTLY NOT INSTALLED. I HAVE ASKED TAMI HAUSER TO PROVIDE ME WITH A CONTACT NAME AND PHONE NUMBER SO THAT I MAY RELAY THIS INFORMATION TO THE DEVELOPER AND REQUEST THAT THE ADDITIONAL CALCULATIONS BE PROVIDED TO THIS OFFICE.
12/13/2007 ASSURANCE - DSD Partial Approval THE SITE WAS CHECKED FOR THE FULL RELEAS OF THE ASSURANCES, IT IS NOT READY AT THIS TIME. THE FOLLOWING LOTS HAVE BEEN COMPLETED AT THIS TIME: 2-5, AND 19-26. LOT #6 IS CURRENTLY UNDER CONSTRUCTION, LOTS 1, 7-16, 27-31 ARE UNDEVELOPED. ALL LOT RELEASES ABOVE THE 75% WILL REQUIRE A COMPLETION BOND FOR ALL REMAINING ASSURABLE ITEMS.
PONDING WATER HAS BEEN NOTED THROUGHOUT THE SITE AT THE FOLLOWING LOCATIONS:
INTERSECTION OF MISSIONDALE RD. AND DUOBA LANE, WEST OF LOTS 9 & 31 ADJACENT TO HANDICAP ACCESS RAMPS.
WEST OF LOTS 27 & 28, AND IN THE INTERSECTION OF DUOBA LANE AND RADEC LANE.
THE BASIN DOES NOT FUNCTION AS SPECIFIED IN THE PIMA COUNTY/CITY OF TUCSON RETENTION DETENTION MANUAL, IT DOES NOT DRAIN WITHIN THE REQUIRED TIME RESTRAINTS.
03/27/2007 ASSURANCE - DSD Partial Approval PREVIOUSLY ALL LOTS ADJACENT TO MISSIONDALE HAD BEEN HELD UNTIL ALL ROADWORK HAD BEEN COMPLETED. THE WESTERN PORTION OF MISSIONDALE HAS BEEN COMPLETED AT THIS TIME WHICH WILL ALLOW FOR THE RELEASE OF ALL LOTS UPTO 75%. TO RELEASE ALL OF THE ASSURANCES FOR THIS PROJECT YOU WILL WILL NEED TO PROVIDE US WITH A COMPLETION BOND FOR ALL REMAINING ASSURABLE ITEMS LEFT TO BE CONSTRUCTED. ALL DRAINAGE ITEMS THAT STILL NEED TO BE COMPLETED AT THIS TIME CAN NOT BE BONDED OUT AND MUST BE COMPLETED PRIOR TO ASKING FOR THE FINAL INSPECTION OF THE SITE.