Permit: TD-DEV-1223-00497
Permit Details
Apply Date:
12/29/2023
Applicant:
Ariel Moore
Description:
New 19 Unit housing development
Permit Reviews
Permit Number - TD-DEV-1223-00497
Permit Status: Complete
Permit Description: New 19 Unit housing development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/03/2024 | DEVELOPMENT PACKAGE NEW v.5 | 08/05/2024 | REQUIRES RESUBMIT |
| 01/04/2024 | DEVELOPMENT PACKAGE NEW v.2 | 01/18/2024 | REQUIRES RESUBMIT |
| 08/08/2024 | DEVELOPMENT PACKAGE NEW v.6 | 08/19/2024 | APPROVED |
| 01/02/2024 | DEVELOPMENT PACKAGE NEW v.1 | 01/04/2024 | REQUIRES RESUBMIT |
| 03/08/2024 | DEVELOPMENT PACKAGE NEW v.3 | 03/22/2024 | REQUIRES RESUBMIT |
| 04/26/2024 | DEVELOPMENT PACKAGE NEW v.4 | 05/26/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TD-DEV-1223-00497
Permit Status: Complete
Permit Description: New 19 Unit housing development
| Date | Description | Comments |
|---|---|---|
| 11/24/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-1223-00497
Permite Description: New 19 Unit housing development
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/28/2025 | For trash and recycling enclosures | N/A | Partial Pass | See checklist items |
| 11/19/2025 | COT - FCON - Fire - Final | N/A | Not Applicable | |
| 12/01/2025 | ENGR Paving | N/A | Not Ready | contractor still placing. AB contractor will call in later this week for AB inspection |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-1223-00497
Permit Description: New 19 Unit housing development
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/12/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre Con completed | |
| 05/06/2025 | ENGR - Drainage Structures | Passed | Drainage structures are complete, this will close out these. | |
| 07/23/2025 | For trash and recycling enclosures | Passed | complete | |
| 11/18/2025 | Passed | |||
| 11/24/2025 | Passed | |||
| 11/18/2025 | Passed | |||
| 11/18/2025 | Passed | |||
| 12/09/2025 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 12/09/2025 | Passed | Wall at temp power location on East border is complete. Drainage blocks in 5' walls are in place. All walls are complete per plans at this point. | ||
| 12/11/2025 | COT - ENGR - Signage Final | Passed | ||
| 12/11/2025 | ENGR Paving | Passed | ||
| 12/11/2025 | Passed | |||
| 12/23/2025 | ENGR Engineering Final | Passed | ||
| 12/29/2025 | LAND Landscape Appearance & Function Final | Passed | ||
| 12/29/2025 | COT - BASN - Drainage/Basin - Condition Inspection | Passed |