Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.4
Permit Number - TD-DEV-1223-00497
Review Name: DEVELOPMENT PACKAGE NEW v.4
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/01/2024 | Site Zoning | APPROVED | |||
| 05/31/2024 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 05/29/2024 | Commercial Plumbing | REQUIRES RESUBMIT | The last three cleanouts have developed lengths in excess of 100 feet. [Second comment: The note, “PROVIDE CO EVERY 100 [feet]” is ambiguous because it does not indicate that the spacing of the cleanouts is based on the developed pipe length.] [Initial comment: Building sewers smaller than 8-inches shall have cleanouts located at intervals of not more than 100-feet apart, measured along the developed pipe length from the upstream entrance of the cleanout. Reference: Section 708.1.2, IPC 2018.] | ||
| 05/31/2024 | Site Engineering | REQUIRES RESUBMIT | 1. Provide detail of gate at access ramp into North Basin. Call out handrail at ramp area. 2. Provide access ramp and gate into West Basin. 3. Per Justin Eder - Provide a stamped structural detail drawing for walls with saturation cut-off walls by engineer present on conference calls. Joshua Garcia joshua.garcia@tucsonaz.gov |
||
| 04/26/2024 | CDRC Application Completeness Express | REVIEW COMPLETED |