Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 03/28/2025 |
|
|
Partial Pass |
I inspected reinforcing for east and west walls. They are poured in place stem walls. 16 yards have been grouted today. Control joints @16’. See checklist items. |
| 04/14/2025 |
|
|
Partial Pass |
5 ' CMU walls ready for grout on north property end south of north basin. Walls should have additional drain openings - not built per plan with decorative block at 6' o.c. Correction will be required prior to final inspection. |
| 04/15/2025 |
|
|
Partial Pass |
See checklist for comments |
| 11/18/2025 |
|
|
Not Ready |
|
| 12/08/2025 |
|
|
Passed |
Wall at temp power location on East border is complete. Drainage blocks in 5' walls are in place. All walls are complete per plans at this point. |