Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Development Package
Address NEW:
5075 E VALENCIA RD
Apply Date:
09/21/2023
Applicant:
Rysheen Cain
Description:
Super Star Car Wash - Valencia and I-10

Permit Reviews

Permit Number - TD-DEV-0923-00401
Permit Status: Inspections complete
Permit Description: Super Star Car Wash - Valencia and I-10
Start Date Submittal Complete Date Status  
01/02/2024 DEVELOPMENT PACKAGE NEW v.2 02/01/2024 REQUIRES RESUBMIT Review Details
09/25/2023 DEVELOPMENT PACKAGE NEW v.1 11/03/2023 REQUIRES RESUBMIT Review Details
02/19/2026 AS-BUILT v.2 02/23/2026 APPROVED Review Details
02/18/2026 AS-BUILT v.1 02/18/2026 REQUIRES RESUBMIT Review Details
02/15/2024 DEVELOPMENT PACKAGE NEW v.3 03/19/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TD-DEV-0923-00401
Permit Status: Inspections complete
Permit Description: Super Star Car Wash - Valencia and I-10
Total Outstanding Activity Conditions - 1
Date Name
10/02/2025 CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TD-DEV-0923-00401
Permite Description: Super Star Car Wash - Valencia and I-10
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
02/12/2026 ENGR Engineering Final N/A Partial Pass 2/12/26
3 Caps labeled "SD" need to replace the sewer caps on the inspection pipes of the underground Storm Water Basin. Disturbed area North of side needs to have refuse removed and be hydroseeded as discussed with contractor. Reschedule this inspection when ready.
08/28/2025 N/A Partial Pass Correct materials are being used according to the manufacturer's specs and design. There is a matt below the basins in this field. All piping has been sealed and rock and fabric installed correctly. Backfill is being completed on the system.
11/14/2025 For trash and recycling enclosures N/A Not Ready 11/14/25
Walls on Vacuum enclosure and Refuse enclosure are complete bollards in. Request inspection on floor rebar mat when ready. Curb that meets the end of the wall is not correct. They should be removed and aligned outside of Gate opening for correct gate clearance.
11/25/2025 N/A Partial Pass 11/25/25
Ok to pour sidewalk ramps on west side of building at midpoint of building. Ok to pour sidewalk ramp to the south of building. Ok to pour scupper walls in same sidewalk. I will get email to contractor confirming this detail. Overflow drain from roof will have to be elbow down under scupper. Use expansion joint material at cold joints of scuppers.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TD-DEV-0923-00401
Permit Description: Super Star Car Wash - Valencia and I-10
Total Completed Inspections - 11
Date Description Inspector Results Comments
06/12/2025 PDSD Engineering Division Pre-Construction SITE Passed In the pre-con it was noticed that the trash enclosure did not meet the city specs. NPPO is next and all 5 of the barrel cactus are missing prior to construction start.
06/16/2025 NPPO Pre-Construction Passed 06/16/25, The 5 barrel cactus are missing, discussed was to replace 1 for 1 at time of landscape going in. Chad will have to decide if this is sufficient.
11/14/2025 ENGR - Drainage Structures Passed 11/14/25
Drain pipe and structures all installed. Remaining drainage surface to Riprap Whia's etc.
01/21/2026 ENGR Grading Final Passed 01/21/26
Grading is almost complete with the exception of basins to the east and asphalt paved area to the north. Contractor will be calling in landscaping, and paving inspections to ensure that these areas are finished correct. Slopes are correct drainage looks good. Water harvesting areas are graded or almost 100% for correct drainage.
02/09/2026 LAND Landscape Appearance & Function Final Passed Details to finish before DP final.
Landscaping- Hydroseed disturbed area two north of site.
DG slope at Southwest of site by sidewalk.
Fix riprap inlet at curb cut at north of site.
Fix tree stakes of multi trunk trees so that just one or two trunks are looped and the rest are not constricted.

Other details:
Paint scuppers
Fix downspout hole so it is 1” Diameter larger than downspout at scuppers.
Paint downspout pipe.
Fix Ramp and panels with bad cross slope.
02/11/2026 COT - ENGR - Signage Final Passed
02/11/2026 Passed
03/04/2026 ENGR Engineering Final Passed
03/09/2026 Passed
03/09/2026 For trash and recycling enclosures Passed
03/09/2026 Passed

Documents

File Name Document Type  
AS-BUILT STAMPED 02.20.2026 SSCW-VALENCIA2025-ASBUILTS-02-10-2026FINAL_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
SSCW VALENCIA_RESPONSE - STORM_V1.PDF DOCUMENTS VIEW
1_ SSCW VALENC - GEOTECHNICAL INVESTIGATION REPORT - SUPER STAR CAR WASH_V1.PDF DOCUMENTS VIEW
102861_CGP20_NEWPERMIT_NOI_CERTIFICATE_V1.PDF DOCUMENTS VIEW
2023-12-26 DRAINAGE REPORT_V2.PDF DOCUMENTS VIEW
APPROVED_3_SSCW-VALENCIA-DPP_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SSCW VALENCIA - I-10 DUST PERMIT_V1.PDF DOCUMENTS VIEW
1_ SSCW VALENC - GEOTECHNICAL INVESTIGATION REPORT - SUPER STAR CAR WASH_V1.PDF PLANS UNDER REVIEW VIEW
1_SSCW VALENCIA I10 DRAINAGE REPORT_V1.PDF PLANS UNDER REVIEW VIEW
1_SCW VALENCIA SWPPP_V1.PDF PLANS UNDER REVIEW VIEW