Permit: TD-DEV-0923-00401
Permit Details
Status:
Inspections Complete
Type:
Development Package
Address:
5075 E VALENCIA RD
Address NEW:
5075 E VALENCIA RD
Apply Date:
09/21/2023
Applicant:
Rysheen Cain
Description:
Super Star Car Wash - Valencia and I-10
Permit Reviews
Permit Number - TD-DEV-0923-00401
Permit Status: Inspections complete
Permit Description: Super Star Car Wash - Valencia and I-10
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/02/2024 | DEVELOPMENT PACKAGE NEW v.2 | 02/01/2024 | REQUIRES RESUBMIT |
| 09/25/2023 | DEVELOPMENT PACKAGE NEW v.1 | 11/03/2023 | REQUIRES RESUBMIT |
| 02/19/2026 | AS-BUILT v.2 | 02/23/2026 | APPROVED |
| 02/18/2026 | AS-BUILT v.1 | 02/18/2026 | REQUIRES RESUBMIT |
| 02/15/2024 | DEVELOPMENT PACKAGE NEW v.3 | 03/19/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0923-00401
Permit Status: Inspections complete
Permit Description: Super Star Car Wash - Valencia and I-10
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0923-00401
Permite Description: Super Star Car Wash - Valencia and I-10
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/12/2026 | ENGR Engineering Final | N/A | Partial Pass | 2/12/26 3 Caps labeled "SD" need to replace the sewer caps on the inspection pipes of the underground Storm Water Basin. Disturbed area North of side needs to have refuse removed and be hydroseeded as discussed with contractor. Reschedule this inspection when ready. |
| 08/28/2025 | N/A | Partial Pass | Correct materials are being used according to the manufacturer's specs and design. There is a matt below the basins in this field. All piping has been sealed and rock and fabric installed correctly. Backfill is being completed on the system. | |
| 11/14/2025 | For trash and recycling enclosures | N/A | Not Ready | 11/14/25 Walls on Vacuum enclosure and Refuse enclosure are complete bollards in. Request inspection on floor rebar mat when ready. Curb that meets the end of the wall is not correct. They should be removed and aligned outside of Gate opening for correct gate clearance. |
| 11/25/2025 | N/A | Partial Pass | 11/25/25 Ok to pour sidewalk ramps on west side of building at midpoint of building. Ok to pour sidewalk ramp to the south of building. Ok to pour scupper walls in same sidewalk. I will get email to contractor confirming this detail. Overflow drain from roof will have to be elbow down under scupper. Use expansion joint material at cold joints of scuppers. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0923-00401
Permit Description: Super Star Car Wash - Valencia and I-10
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | In the pre-con it was noticed that the trash enclosure did not meet the city specs. NPPO is next and all 5 of the barrel cactus are missing prior to construction start. | |
| 06/16/2025 | NPPO Pre-Construction | Passed | 06/16/25, The 5 barrel cactus are missing, discussed was to replace 1 for 1 at time of landscape going in. Chad will have to decide if this is sufficient. | |
| 11/14/2025 | ENGR - Drainage Structures | Passed | 11/14/25 Drain pipe and structures all installed. Remaining drainage surface to Riprap Whia's etc. |
|
| 01/21/2026 | ENGR Grading Final | Passed | 01/21/26 Grading is almost complete with the exception of basins to the east and asphalt paved area to the north. Contractor will be calling in landscaping, and paving inspections to ensure that these areas are finished correct. Slopes are correct drainage looks good. Water harvesting areas are graded or almost 100% for correct drainage. |
|
| 02/09/2026 | LAND Landscape Appearance & Function Final | Passed | Details to finish before DP final. Landscaping- Hydroseed disturbed area two north of site. DG slope at Southwest of site by sidewalk. Fix riprap inlet at curb cut at north of site. Fix tree stakes of multi trunk trees so that just one or two trunks are looped and the rest are not constricted. Other details: Paint scuppers Fix downspout hole so it is 1” Diameter larger than downspout at scuppers. Paint downspout pipe. Fix Ramp and panels with bad cross slope. |
|
| 02/11/2026 | COT - ENGR - Signage Final | Passed | ||
| 02/11/2026 | Passed | |||
| 03/04/2026 | ENGR Engineering Final | Passed | ||
| 03/09/2026 | Passed | |||
| 03/09/2026 | For trash and recycling enclosures | Passed | ||
| 03/09/2026 | Passed |