Parcel: 14036349A


Addresses:

5075 E VALENCIA RD


Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0923-00401

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
10/02/2025 Partial Pass Contractor, good to pour the curb per the changes of the engineer of record on the west side of the building
10/23/2025 Partial Pass Contractors good to pour the curb on the south west side. The sidewalk on the west side is not ready yet. Contractor will call in for another inspection.
10/24/2025 Partial Pass compaction for sidewalk sub grade is good, >95%. Layout/forms are correct for proper dimensions and slopes. Okay to pour.
11/14/2025 Not Ready
11/24/2025 Partial Pass 11/25/25
Ok to pour sidewalk ramps on west side of building at midpoint of building. Ok to pour sidewalk ramp to the south of building. Ok to pour scupper walls in same sidewalk. I will get email to contractor confirming this detail. Overflow drain from roof will have to be elbow down under scupper. Use expansion joint material at cold joints of scuppers.