Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2026 | Partial Pass | 1/6/26 South 5’ Sidewalk Ramp and approach to the ROW sidewalk. contractor will send me good pictures of 5’ landing with slopes less than 2% above ramp. When pictures received and ok’ed Okay to pour sidewalk. In addition North Refuse enclosure needs to be extended in height. Contractor will send good pictures of epoxy fixed rebar for top course of wall. |
||
| 01/12/2026 | Partial Pass | |||
| 03/09/2026 | Passed | |||
| 10/02/2025 | Partial Pass | Contractor, good to pour the curb per the changes of the engineer of record on the west side of the building | ||
| 10/23/2025 | Partial Pass | Contractors good to pour the curb on the south west side. The sidewalk on the west side is not ready yet. Contractor will call in for another inspection. | ||
| 10/24/2025 | Partial Pass | compaction for sidewalk sub grade is good, >95%. Layout/forms are correct for proper dimensions and slopes. Okay to pour. | ||
| 11/14/2025 | Not Ready | |||
| 11/24/2025 | Partial Pass | 11/25/25 Ok to pour sidewalk ramps on west side of building at midpoint of building. Ok to pour sidewalk ramp to the south of building. Ok to pour scupper walls in same sidewalk. I will get email to contractor confirming this detail. Overflow drain from roof will have to be elbow down under scupper. Use expansion joint material at cold joints of scuppers. |