Permit: TD-DEV-0923-00385
Permit Details
Apply Date:
09/01/2023
Applicant:
Alicia Simmons
Description:
Rev 1 - submitted 10.23.2025 - Update to landscaping, doorways ** New Buildings, parking and landscape for Teen Challenge.
Permit Reviews
Permit Number - TD-DEV-0923-00385
Permit Status: Complete
Permit Description: Rev 1 - submitted 10.23.2025 - Update to landscaping, doorways ** New Buildings, parking and landscape for Teen Challenge.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/06/2023 | DEVELOPMENT PACKAGE NEW v.1 | 10/19/2023 | REQUIRES RESUBMIT |
| 01/19/2024 | DEVELOPMENT PACKAGE NEW v.3 | 01/25/2024 | APPROVED |
| 10/23/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 11/24/2025 | APPROVED |
| 11/22/2023 | DEVELOPMENT PACKAGE NEW v.2 | 01/04/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0923-00385
Permite Description: Rev 1 - submitted 10.23.2025 - Update to landscaping, doorways ** New Buildings, parking and landscape for Teen Challenge.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2025 | N/A | Not Applicable | Contractor is pouring ROW sidewalk. I talked to him on phone about inspections he will need to request. | |
| 10/03/2025 | For trash and recycling enclosures | N/A | Partial Pass | Reinforcement is good, depth is good, slope is accurate - slab is formed per plans; okay to pour. |
| 12/16/2025 | N/A | Partial Pass | Contractor can pour for on-site sign footer | |
| 12/30/2025 | N/A | Partial Pass | Contractor, good to backfill the storm drain pipe along Oracle Road. Contractor also cap the existing 30 inch RCP pipe that is abandoned. | |
| 01/09/2026 | ENGR - Drainage Structures | N/A | Partial Pass | Infiltration chambers along Oracle Rd, two sections immediately north of southern entrance, 10 chambers total: These are set correctly and pvc connection pipe is in place. Okay to backfill. |
| 12/11/2024 | Consultation SITE | N/A | Partial Pass | I informed the contractor he need to call every two weeks for swap inspections grading, rebar inspections, so on so forth with the engineering department |
| 12/23/2025 | Grading Progress ENGR | N/A | Partial Pass | Contractor just started grading the parking lot area on the Oracle roadside. Continue grading. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0923-00385
Permit Description: Rev 1 - submitted 10.23.2025 - Update to landscaping, doorways ** New Buildings, parking and landscape for Teen Challenge.
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/04/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Contractor called in for the wrong inspection contractor needed an 8 inch HDP pipe or stormwater everything’s good and inform the contractor that I need compaction test on the backfield | |
| 03/25/2026 | For trash and recycling enclosures | Passed | ||
| 03/25/2026 | Passed | |||
| 03/25/2026 | Passed | |||
| 03/25/2026 | ENGR - Drainage Structures | Passed | ||
| 04/15/2026 | Grading Progress ENGR | Passed | ||
| 04/15/2026 | Passed | |||
| 04/22/2026 | ENGR Paving | Passed | ||
| 04/27/2026 | Passed | |||
| 04/28/2026 | LAND Landscape Appearance & Function Final | Passed | ||
| 04/28/2026 | Passed | |||
| 04/28/2026 | ENGR Engineering Final | Passed |