Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 01/09/2026 |
|
|
Partial Pass |
Infiltration chambers along Oracle Rd, two sections immediately north of southern entrance, 10 chambers total: These are set correctly and pvc connection pipe is in place. Okay to backfill. |
| 02/21/2025 |
|
|
Partial Pass |
Behind buildings on the west side, good to backfill 02/21/25 |
| 02/26/2025 |
|
|
Partial Pass |
contractors good to backfill the 12 storm drain on the north west side |
| 03/25/2026 |
|
|
Passed |
|
| 04/25/2025 |
|
|
Partial Pass |
Okay to backfill drainage pipe up to staff living building. |
| 06/23/2025 |
|
|
Partial Pass |
Contractor installed 12 inch HDP between building one and two good to backfill |
| 12/29/2025 |
|
|
Not Ready |
Contractor needs to cap the old existing RCP pipe running into the job site off of Oracle. |
| 12/30/2025 |
|
|
Partial Pass |
Contractor, good to backfill the storm drain pipe along Oracle Road. Contractor also cap the existing 30 inch RCP pipe that is abandoned. |