Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date |
Description |
Inspector |
Results |
Comments |
| 01/21/2026 |
Grading Progress ENGR |
|
Partial Pass |
The contractor and myself streamlined the parking lot on the north end. Contractor was low and high in some areas. And repairing ASAP. Contractor will pave tomorrow morning. |
| 01/27/2026 |
Grading Progress ENGR |
|
Partial Pass |
Contractor is good to pave. The employees parking area looks good for grade. |
| 03/19/2026 |
Grading Progress ENGR |
|
Partial Pass |
contractor is good to place a B on the north east quadrant of the project |
| 03/25/2026 |
Grading Progress ENGR |
|
Partial Pass |
The front parking lot off of Oracle rd.is good for paving |
| 12/23/2025 |
Grading Progress ENGR |
|
Partial Pass |
Contractor just started grading the parking lot area on the Oracle roadside. Continue grading. |