Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
10071 E OLD VAIL RD
Apply Date:
06/14/2023
Applicant:
Atwell Submittals
Description:
New Salad and Go 1184

Permit Reviews

Permit Number - TD-DEV-0623-00278
Permit Status: Complete
Permit Description: New Salad and Go 1184
Start Date Submittal Complete Date Status  
06/14/2023 DEVELOPMENT PACKAGE NEW v.1 07/18/2023 REQUIRES RESUBMIT Review Details
08/29/2023 DEVELOPMENT PACKAGE NEW v.3 09/22/2023 REQUIRES RESUBMIT Review Details
12/08/2023 DEVELOPMENT PACKAGE NEW v.6 12/08/2023 REQUIRES RESUBMIT Review Details
08/11/2023 DEVELOPMENT PACKAGE NEW v.2 08/16/2023 REQUIRES RESUBMIT Review Details
10/06/2023 DEVELOPMENT PACKAGE NEW v.4 10/24/2023 REQUIRES RESUBMIT Review Details
11/17/2023 DEVELOPMENT PACKAGE NEW v.5 12/01/2023 REQUIRES RESUBMIT Review Details
12/08/2023 DEVELOPMENT PACKAGE NEW v.7 01/18/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TD-DEV-0623-00278
Permite Description: New Salad and Go 1184
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
04/17/2024 Final inspection to ensure all landscape and water harvesting SITE N/A Not Ready Contractor has not started on the water harvesting
05/13/2024 SITE - Stormwater Final Inspection N/A Partial Pass contractor did not finish the water harvesting on the west side. Contractor needs to speak to the engineer of record to redesign the water harvesting on the west side, and on the north side of the project
05/14/2024 PDSD Site/Engineering Division - Landscaping N/A Partial Pass Contractor needs to complete the planning of the trees on the south end and complete the water harvesting on the west end of the building and on the north end of the building
05/14/2024 ENGR Engineering Final N/A Partial Pass Contractor needs to complete the installation of the plants on the south end of the building finished the water harvesting on the west end, and on the north end of the building

Completed Inspections

Permit Status: Complete
Permit Number: TD-DEV-0623-00278
Permit Description: New Salad and Go 1184
Total Completed Inspections - 19
Date Description Inspector Results Comments
02/02/2024 PDSD Engineering Division Pre-Construction SITE Passed Completed pre-construction meeting with Carlos Gomez and reviewed existing parking lot and made them aware of the (2) handicap parking spaces on the far NW end of site appeared to be well over 2% and need to be addressed along with the (2) handicap parking spaces at the center West location of existing parking lot need to be verified space to the North appears to be over 2%.

The layout for trash enclosure was given to Carlos and we went over all footer, height of walls, and bollard details and explained that we will need to inspect the enclosure.

The area on the West side of site between Big O tires will have wattle installed on Monday of next week per Carlos.

Carlos will provide landscape invoice when landscape is completed.
03/26/2024 SITE - Stormwater Setup and Controls Passed
04/02/2024 PDSD Site/Engineering Division - NPPO Passed
04/02/2024 SITE - SWPPP Violation Notice Passed There is no SWPPP violation notice
04/02/2024 SITE - SWPPP Correction Notice Passed There is no, SWPP correction notice
04/02/2024 COT - SITE - Zoning Intermediate Passed
04/02/2024 SITE - Zoning Compliance Passed
05/08/2024 SITE - Zoning Final Passed
05/13/2024 COT - ENGR - Signage Final Passed
05/17/2024 Final inspection to ensure all landscape and water harvesting SITE Passed
05/13/2024 City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection Passed
05/13/2024 COT - ENGR - Stormwater Passed
05/13/2024 ENGR - Drainage Structures Passed
05/17/2024 SITE Passed Rain Water Harvesting is questionable along the Southern Portion of the Site due to existing grade changes for the nex sidewalk and the existing Roadway. Engineer of Record has been asked to provide documentaion showing how the CRWH has been met for this site.
05/17/2024 SITE - Stormwater Follow-up Passed
05/14/2024 COT - ENGR - Site - Assurance Release Passed
07/29/2024 SITE - Stormwater Final Inspection Passed The commercial stormwater for this site has been completed as most of the site is totally done and being occupied
10/03/2024 PDSD Site/Engineering Division - Landscaping Passed
10/03/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
APPROVED_SUB 5 - DEV PACKAGE_SAG OVP 1184_V4_V1_V1.PDF APPROVED_SUB 5 - DEV PACKAGE_SAG OVP 1184_V4_V1_V1 VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SEWER DESIGN REPORT - SALAD AND GO 1184 - V1_V1.PDF PLANS UNDER REVIEW VIEW