Permit: TD-DEV-0623-00278
Permit Details
Status:
Complete
Type:
Development Package
Address:
10071 E OLD VAIL RD
Address NEW:
10071 E OLD VAIL RD
Apply Date:
06/14/2023
Applicant:
Atwell Submittals
Description:
New Salad and Go 1184
Permit Reviews
Permit Number - TD-DEV-0623-00278
Permit Status: Complete
Permit Description: New Salad and Go 1184
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/14/2023 | DEVELOPMENT PACKAGE NEW v.1 | 07/18/2023 | REQUIRES RESUBMIT |
| 08/29/2023 | DEVELOPMENT PACKAGE NEW v.3 | 09/22/2023 | REQUIRES RESUBMIT |
| 12/08/2023 | DEVELOPMENT PACKAGE NEW v.6 | 12/08/2023 | REQUIRES RESUBMIT |
| 08/11/2023 | DEVELOPMENT PACKAGE NEW v.2 | 08/16/2023 | REQUIRES RESUBMIT |
| 10/06/2023 | DEVELOPMENT PACKAGE NEW v.4 | 10/24/2023 | REQUIRES RESUBMIT |
| 11/17/2023 | DEVELOPMENT PACKAGE NEW v.5 | 12/01/2023 | REQUIRES RESUBMIT |
| 12/08/2023 | DEVELOPMENT PACKAGE NEW v.7 | 01/18/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0623-00278
Permite Description: New Salad and Go 1184
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2024 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | Contractor has not started on the water harvesting |
| 05/13/2024 | SITE - Stormwater Final Inspection | N/A | Partial Pass | contractor did not finish the water harvesting on the west side. Contractor needs to speak to the engineer of record to redesign the water harvesting on the west side, and on the north side of the project |
| 05/14/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | Contractor needs to complete the planning of the trees on the south end and complete the water harvesting on the west end of the building and on the north end of the building |
| 05/14/2024 | ENGR Engineering Final | N/A | Partial Pass | Contractor needs to complete the installation of the plants on the south end of the building finished the water harvesting on the west end, and on the north end of the building |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0623-00278
Permit Description: New Salad and Go 1184
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Completed pre-construction meeting with Carlos Gomez and reviewed existing parking lot and made them aware of the (2) handicap parking spaces on the far NW end of site appeared to be well over 2% and need to be addressed along with the (2) handicap parking spaces at the center West location of existing parking lot need to be verified space to the North appears to be over 2%. The layout for trash enclosure was given to Carlos and we went over all footer, height of walls, and bollard details and explained that we will need to inspect the enclosure. The area on the West side of site between Big O tires will have wattle installed on Monday of next week per Carlos. Carlos will provide landscape invoice when landscape is completed. |
|
| 03/26/2024 | SITE - Stormwater Setup and Controls | Passed | ||
| 04/02/2024 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 04/02/2024 | SITE - SWPPP Violation Notice | Passed | There is no SWPPP violation notice | |
| 04/02/2024 | SITE - SWPPP Correction Notice | Passed | There is no, SWPP correction notice | |
| 04/02/2024 | COT - SITE - Zoning Intermediate | Passed | ||
| 04/02/2024 | SITE - Zoning Compliance | Passed | ||
| 05/08/2024 | SITE - Zoning Final | Passed | ||
| 05/13/2024 | COT - ENGR - Signage Final | Passed | ||
| 05/17/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 05/13/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
| 05/13/2024 | COT - ENGR - Stormwater | Passed | ||
| 05/13/2024 | ENGR - Drainage Structures | Passed | ||
| 05/17/2024 | SITE | Passed | Rain Water Harvesting is questionable along the Southern Portion of the Site due to existing grade changes for the nex sidewalk and the existing Roadway. Engineer of Record has been asked to provide documentaion showing how the CRWH has been met for this site. | |
| 05/17/2024 | SITE - Stormwater Follow-up | Passed | ||
| 05/14/2024 | COT - ENGR - Site - Assurance Release | Passed | ||
| 07/29/2024 | SITE - Stormwater Final Inspection | Passed | The commercial stormwater for this site has been completed as most of the site is totally done and being occupied | |
| 10/03/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 10/03/2024 | ENGR Engineering Final | Passed |