Permit Details

Status:
Inspections
Type:
Development Package
Address NEW:
10129 E GOLF LINKS RD
Apply Date:
06/08/2023
Applicant:
Description:
New Storage Facility

Permit Reviews

Permit Number - TD-DEV-0623-00271
Permit Status: Inspections
Permit Description: New Storage Facility
Start Date Submittal Complete Date Status  
04/25/2024 DEVELOPMENT PACKAGE NEW v.4 06/27/2024 APPROVED Review Details
06/08/2023 DEVELOPMENT PACKAGE NEW v.1 07/15/2023 REQUIRES RESUBMIT Review Details
08/24/2023 DEVELOPMENT PACKAGE NEW v.2 09/22/2023 REQUIRES RESUBMIT Review Details
03/15/2024 DEVELOPMENT PACKAGE NEW v.3 04/16/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TD-DEV-0623-00271
Permit Status: Inspections
Permit Description: New Storage Facility
Total Outstanding Activity Conditions - 1
Date Name
10/02/2025 CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT

Outstanding Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0623-00271
Permite Description: New Storage Facility
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
09/18/2025 NPPO Monitoring N/A Complete (Recurring) Plants have been moved to nursery and verified, temp irrigation is in place, NPPO is good.
10/30/2025 ENGR - Drainage Structures N/A Partial Pass 5 headwalls along South of site, two require an extra horizontal reinforcement bar at the bottom, once corrected, okay to pour.
11/07/2025 N/A Partial Pass Retaining wall on East border: forms are proper dimensions, reinforcement placement is good. Okay to pour wall.
12/03/2025 ENGR Paving N/A Partial Pass 12/3/25
Paving inspection for asphalt paving to be placed 7:30AM. Compaction is being tested at the same time as inspection. Results so far have all complied at 100% or above. Paving will be done in two lifts. First lift 1.5" and then second lift later 1.5". contractor will send me pictures of areas that needed to be scraped and rolled so all areas are compacted with no loose material. Contractor will start paving at the northwest side of site and will leave the area around the refuse enclosures unpaved and then continue south and around the building all the way to the northeast. Okay to pave this area, pending pictures, complying compaction tests in all areas and weather permitting.
10/22/2025 Consultation SITE N/A Partial Pass Doctor called in for consultation on the RCP pipe that’s at the entryway of the project installed 77 lineal feet of RCP pipe good to backfill
12/17/2025 N/A Partial Pass Curb forms by refuse enclosures are set properly. Okay to pour.
12/18/2025 For trash and recycling enclosures N/A Not Ready Apron Mats not ready. Will push pour from 8:00 to 10:00 tomorrow morning.

Completed Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0623-00271
Permit Description: New Storage Facility
Total Completed Inspections - 4
Date Description Inspector Results Comments
08/18/2025 NPPO Pre-Construction Passed Plants have been tagged and flagged for preservation in accordance with NPPO. Okay to begin grubbing.
09/09/2025 SITE - Stormwater Setup and Controls Passed Initial stormwater measures are in place, CGP will need to be updated to the 2025 permit. Continued site maintenance will be monitored.
09/08/2025 PDSD Engineering Division Pre-Construction SITE Passed Pre-construction meeting is complete. Once all stormwater controls are in place, “Stormwater Initial” inspection should be scheduled. Okay to begin initial land clearing prior to plant relocation.
11/21/2025 Passed 11/21/25
Subgrade of PAAL from ROW to end of radius curves on curbs East and West. Contractor will place 4" ABC with 3" of Asphalt in all of this area in PAAL and parking spaces. Medium duty in plans. Compaction testing of area complies. Submit compaction reports. String line between curbs and hubs is good. No areas that are too high. Some areas are deeper but contractor will increase AB thickness in these areas. AB will be checked with Blue Tops before paving. Okay to place AB in this area. All Subgrade has now been inspected in Paved Areas. Intention is to have all AB inspected at same time, with tolerance of .25".
Request Paving Inspection when ABC is ready.

Scheduled Inspections

Scheduled Inspections - TD-DEV-0623-00271
Status: Inspections
Description: New Storage Facility
Scheduled Date Description Entered By Entered Date
12/19/2025 For trash and recycling enclosures Scheduled
12/30/2025 SITE - Stormwater Follow-up Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
TD-DEV-0623-00271 CAP GOLFLINKS CIVILSETF 04182024 DIGSIG_V1.PDF DOCUMENTS VIEW