Inspection Status: Passed

Inspection History: Consultation SITE

Date Description Inspector Results Comments
05/22/2026 Consultation SITE Passed Depths of water harvesting areas are good, okay for planting.
05/29/2026 Consultation SITE Passed Site visit to discuss water flow issues: Areas of concentrated water flow listed below require erosion control measures, the marked up plan of page C201 proposing riprap splash pads is an acceptable solution. Areas of concern are: 2 culvert outlets on south side, SW parking lot transition to basin P1, basin P1 outflow pipe, downspout scupper on west side, 2 additional downspouts on west side, basin P2 outflow pipe, 2 curb cuts on east side PAAL, 2 ends of retaining wall where flow will concentrate.
06/02/2026 Consultation SITE Passed Detention Area P2 outlet structure: okay to core holes below grate invert at 9" depth to achieve proper retention height, same as was done in Area P1.
10/16/2025 Consultation SITE Partial Pass Site consultation to review SWPPP updates. Book has been replaced due to previous water damage, Porta-potty spill has been remediated, porta-potties are staked down now. Wattle has been refreshed throughout site. *One area of issue behind trailer: wattle isn't in contact with the ground, rills need to be filled in. Requested that ADEQ sign be moved closer to public view.
10/22/2025 Consultation SITE Partial Pass Doctor called in for consultation on the RCP pipe that’s at the entryway of the project installed 77 lineal feet of RCP pipe good to backfill
12/17/2025 Consultation SITE Partial Pass In order to use adjacent property for employee parking, a Temporary Use Permit will be required.