Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-0623-00271
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2025 | Partial Pass | PAAL on East side of project: sub-grade compaction, slope, and elevation is good. Okay to place AB. | ||
| 11/20/2025 | Partial Pass | 11/20/25 Subgrade of west parking parking area. From the PAAL starting at headwall of the basin and end of radius in the curb at drive way in from Golf Links, over to the curb ramps to the North end. Contractor will place 4" ABC with 3" of Asphalt in all of this area in PAAL and parking spaces. Medium duty in plans. Compaction testing of area complies. String line between curbs and hubs is good. No areas that are too high. Some areas are deeper but contractor will increase AB thickness in these areas. AB will be checked with Blue Tops before paving. Okay to place ABC in this area. Request inspection again when ABC is ready. |
||
| 11/21/2025 | Passed | 11/21/25 Subgrade of PAAL from ROW to end of radius curves on curbs East and West. Contractor will place 4" ABC with 3" of Asphalt in all of this area in PAAL and parking spaces. Medium duty in plans. Compaction testing of area complies. Submit compaction reports. String line between curbs and hubs is good. No areas that are too high. Some areas are deeper but contractor will increase AB thickness in these areas. AB will be checked with Blue Tops before paving. Okay to place AB in this area. All Subgrade has now been inspected in Paved Areas. Intention is to have all AB inspected at same time, with tolerance of .25". Request Paving Inspection when ABC is ready. |