Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0623-00271

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
11/14/2025 Partial Pass PAAL on East side of project: sub-grade compaction, slope, and elevation is good. Okay to place AB.
11/20/2025 Partial Pass 11/20/25
Subgrade of west parking parking area. From the PAAL starting at headwall of the basin and end of radius in the curb at drive way in from Golf Links, over to the curb ramps to the North end. Contractor will place 4" ABC with 3" of Asphalt in all of this area in PAAL and parking spaces. Medium duty in plans.
Compaction testing of area complies. String line between curbs and hubs is good. No areas that are too high. Some areas are deeper but contractor will increase AB thickness in these areas. AB will be checked with Blue Tops before paving. Okay to place ABC in this area. Request inspection again when ABC is ready.
11/21/2025 Passed 11/21/25
Subgrade of PAAL from ROW to end of radius curves on curbs East and West. Contractor will place 4" ABC with 3" of Asphalt in all of this area in PAAL and parking spaces. Medium duty in plans. Compaction testing of area complies. Submit compaction reports. String line between curbs and hubs is good. No areas that are too high. Some areas are deeper but contractor will increase AB thickness in these areas. AB will be checked with Blue Tops before paving. Okay to place AB in this area. All Subgrade has now been inspected in Paved Areas. Intention is to have all AB inspected at same time, with tolerance of .25".
Request Paving Inspection when ABC is ready.