Permit: TD-DEV-0423-00197
Permit Details
Status:
Inspections
Type:
Development Package
Address:
5386 S NOGALES HY
Address NEW:
5386 S NOGALES HY
Apply Date:
04/01/2023
Applicant:
Charlie Buchanan
Description:
*Revision 2 started 1/2/25 *Revision #1 started 4/5/24 (drainage)* Rodeo Addition No. 4, Lots 1-18, An FLD Subdivision
Permit Reviews
Permit Number - TD-DEV-0423-00197
Permit Status: Inspections
Permit Description: *Revision 2 started 1/2/25 *Revision #1 started 4/5/24 (drainage)* Rodeo Addition No. 4, Lots 1-18, An FLD Subdivision
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/03/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/04/2023 | REQUIRES RESUBMIT |
| 05/13/2024 | DEVELOPMENT PACKAGE REVIEW v.2 | 05/16/2024 | REQUIRES RESUBMIT |
| 01/02/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 01/15/2025 | REQUIRES RESUBMIT |
| 05/17/2024 | DEVELOPMENT PACKAGE REVIEW v.3 | 05/17/2024 | APPROVED |
| 07/19/2023 | DEVELOPMENT PACKAGE NEW v.1 | 09/12/2023 | APPROVED |
| 04/04/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 06/12/2023 | REQUIRES RESUBMIT |
| 01/28/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 02/21/2025 | APPROVED |
| 04/05/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 05/08/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0423-00197
Permite Description: *Revision 2 started 1/2/25 *Revision #1 started 4/5/24 (drainage)* Rodeo Addition No. 4, Lots 1-18, An FLD Subdivision
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/21/2025 | N/A | Partial Pass | Screen wall north of lot 1 is 4’ high and ready for grout. Reinforcing correct. Vibrate all grouted cells. Screen wall north of lot 5 1 is 4’ high and ready for grout. Reinforcing correct. Vibrate all grouted cells. Screen Wall south of lot 10. Footing good and reinforcement spacing correct. Okay to build up the first 4 ft. then call in pre grout inspection. |
|
| 07/25/2025 | N/A | Partial Pass | Okay to pour sidewalk at all the units repaired. | |
| 08/27/2025 | COT - BASN - Drainage/Basin - Condition Inspection | N/A | Re-inspection required | Concrete spoils, refuse and sediment from disturbed slopes needs to be cleaned out of basins from common area B East of development and DG needs to be installed per plan to stabilize slopes per plan. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0423-00197
Permit Description: *Revision 2 started 1/2/25 *Revision #1 started 4/5/24 (drainage)* Rodeo Addition No. 4, Lots 1-18, An FLD Subdivision
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/17/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Met with habitat for Humanity and Desert Earth to discuss the upcoming Project and when they plan on starting the project officially. Currently they will be looking at the kickoff for this site to be done within the first week of June. They have been reminded to schedule another Pre-con when they will be clearing the site of all the excess vegetation and installing all of their required SWPPP Controls, and Officially Post the site for the Construction. |