Inspection History Details
Inspection Status: Not Ready
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2025 | Not Ready | |||
| 04/07/2025 | Partial Pass | Forms are correct to pour sidewalk in front of lots 11 through 13. | ||
| 04/09/2025 | Partial Pass | See checklist items for details. | ||
| 04/24/2025 | Partial Pass | Sidewalk forms in front of lots 1 through 4 are ready to pour. | ||
| 06/12/2025 | Canceled | |||
| 07/24/2025 | Not Ready | 7/23/25 Repair Panels where BWV were installed. Subgrade is compacted correct. Clean out all loose dirt and debris. There does need to be 1/2” x 4" bituminous filler at the edges of the new panel where it butts up to adjacent concrete. Traffic rated BWV covers and clean out rims also need to be at same grade with adjacent panels. Use straight edge to verify. None are ready yet but I will be back tomorrow around 2:00 to reinspect. |
||
| 07/25/2025 | Partial Pass | Okay to pour sidewalk at all the units repaired. |