Permit: TD-DEV-0324-00096
Permit Details
Apply Date:
03/21/2024
Applicant:
Benjamin Jessop
Description:
Rev 1 - 7/18/25 - EV chargers; Expansion of existing Walmart from 87,000 SF to 164,000 SF on 11.71 acres.
Permit Reviews
Permit Number - TD-DEV-0324-00096
Permit Status: Issued
Permit Description: Rev 1 - 7/18/25 - EV chargers; Expansion of existing Walmart from 87,000 SF to 164,000 SF on 11.71 acres.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/08/2024 | DEVELOPMENT PACKAGE NEW v.3 | 12/18/2024 | REQUIRES RESUBMIT |
| 09/03/2025 | DEVELOPMENT PACKAGE NEW REVISION v.3 | 09/25/2025 | APPROVED |
| 07/22/2024 | DEVELOPMENT PACKAGE NEW v.2 | 09/27/2024 | REQUIRES RESUBMIT |
| 07/30/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 08/22/2025 | REQUIRES RESUBMIT |
| 03/22/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/08/2024 | REQUIRES RESUBMIT |
| 11/04/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 11/26/2025 | APPROVED |
| 07/18/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 07/25/2025 | REQUIRES RESUBMIT |
| 10/13/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 10/13/2025 | REQUIRES RESUBMIT |
| 01/07/2025 | DEVELOPMENT PACKAGE NEW v.4 | 02/20/2025 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0324-00096
Permite Description: Rev 1 - 7/18/25 - EV chargers; Expansion of existing Walmart from 87,000 SF to 164,000 SF on 11.71 acres.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2025 | Consultation SITE | N/A | Partial Pass | Contractors going to start installing the RCP’s in the back of the Walmart will call in for another inspection for the trench and the bedding tomorrow |
| 07/23/2025 | ENGR - Drainage Structures | N/A | Partial Pass | 7/23/25 Okay to pour Catch Basin 309. Unable to see Joint to Drainage pipe so do not backfill until we see it again after forms are stripped. Call us back out to reinspect. |
| 11/10/2025 | N/A | Partial Pass | 11/10/25 Approx 100' 12" RCP at 1% running up grade, west in front of store, from manhole at NE of building. Trench correct, shading correct. Ok to backfill. Submit compaction reports to the portal. Inspector will be on site at 4:00 am Wednesday for next section in front of entrance. |
|
| 11/14/2025 | ENGR Paving | N/A | Partial Pass | 11/14/25 PCCP 6" north of store from last cold joint at start of Catch Basin in middle of driveline. Submit compaction reports in Subgrade and AB to the portal. Expansion material at cold joints and dowels at joint of previous pour. Spoils pile needs to be cleaned up to south of catch basin. Send picture showing this. Okay to place 6" concrete paving up to expansion joint in gutter curb approximately 20 ft east of manhole. Submit compaction reports and cylinders results to the permit. Okay to pour further west pending pictures of correct grading and depths and pending compaction reports up to and past stoop and man hole west to corner of building. |
| 12/16/2025 | N/A | Partial Pass | 12/16/25 Continuation of sidewalk w/ turndown 1'-4" with bollards @ 8' OC going east. From bollard 13 to 17 from #1 at Entryway. Expansion material is in place and dowels in place at 2'. Stoop for new 3' Doorway not on plans being cut into wall, stoop poured behind bollard 18. Check for approval. Forms good, depth correct. Ok to pour sidewalk |
|
| 02/19/2026 | N/A | Not Ready | Contractor has not completed the installation of the plants. Will call for reinspection at a later date. | |
| 12/18/2025 | N/A | Partial Pass | 12/18/25 Sidewalk continues east to SE corner of building. Submit Subgrade density reports. Forms and turndowns at asphalt and planters correct. Expansion material correct at cold joints. Slopes correct. Dowels placed at 2' at cold joints. Okay to pour sidewalk. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0324-00096
Permit Description: Rev 1 - 7/18/25 - EV chargers; Expansion of existing Walmart from 87,000 SF to 164,000 SF on 11.71 acres.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | For the contractor to call in every two weeks for the swap, and as needed, also inform the contractor that we would need to review all the compaction test and the trench lines all the underground storm drains as it has been built |