| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2025 | Partial Pass | 12/10/25 Seven 6" pipe Bollards are spaced 5' OC in front of Entryway. Depth of Footers is 51". As you go east the entryway becomes block wall adjacent to sidewalk. Here the spacing of 7 more is 8' OC per plans and accepted by Tsmr. Okay to pour bollards. |
||
| 12/16/2025 | Partial Pass | 12/16/25 Continuation of sidewalk w/ turndown 1'-4" with bollards @ 8' OC going east. From bollard 13 to 17 from #1 at Entryway. Expansion material is in place and dowels in place at 2'. Stoop for new 3' Doorway not on plans being cut into wall, stoop poured behind bollard 18. Check for approval. Forms good, depth correct. Ok to pour sidewalk |