| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2025 | ENGR - Drainage Structures | Partial Pass | Contractor removed four sticks of 52 inch RCP. Started replacing the 52 inch with new 52 inch RCP for tomorrow to inspect the pipes that are being installed today. | |
| 05/15/2025 | ENGR - Drainage Structures | Partial Pass | Contractor installed four sticks of 52 inch RCP on the north end of the building also formed up an a dot collar around the 54 inch connection | |
| 05/20/2025 | ENGR - Drainage Structures | Not Ready | Contractor will reschedule for tomorrow when they set the manhole and the storm drain | |
| 05/21/2025 | ENGR - Drainage Structures | Not Ready | Texas gonna reschedule spectrum for Tuesday morning | |
| 06/03/2025 | ENGR - Drainage Structures | Not Ready | Contractor finish installing the 54 inch RCP’s and they backfilled it. They haven’t started on the 12 inch RCP yet. | |
| 06/05/2025 | ENGR - Drainage Structures | Partial Pass | Contractor installed 40 lineal feet of 12 inch RCP up to the basin at a 10% slope. They’re good to backfill. | |
| 06/06/2025 | ENGR - Drainage Structures | Partial Pass | Location, type, slope, depth, and connections are good. Okay to backfill 12" RCP run along East side of building. | |
| 06/09/2025 | ENGR - Drainage Structures | Partial Pass | Contractor continues to install 12 inch RCP on the east end of the project | |
| 06/10/2025 | ENGR - Drainage Structures | Partial Pass | 24" precast 45 degree from existing to new installed at South of project, okay to backfill to top of pipe. | |
| 06/11/2025 | ENGR - Drainage Structures | Partial Pass | Second 45 on the 24" RCP at north side and straight run up to proposed manhole connection with 54" RCP is complete and okay to backfill. 12" lateral connections will be done at a later date. | |
| 06/12/2025 | ENGR - Drainage Structures | Partial Pass | Manhole is in location at South of project but final placement is being worked on. Okay to continue with manhole and make RCP connections. | |
| 06/25/2025 | ENGR - Drainage Structures | Not Ready | Contractor will call tomorrow for an inspection about 1 o’clock | |
| 06/26/2025 | ENGR - Drainage Structures | Partial Pass | Manhole structure on North side is in place, 54"/24" inlet & 72" outlet connections/placement are good, there is a drawing modification being worked on to adjust the slopes to achieve positive drainage. | |
| 06/27/2025 | ENGR - Drainage Structures | Partial Pass | ADOT connection on 72" RCP, new to existing is to spec. 2-0 coverage beyond pipe ends, 5 total ties, and overall thickness are good. Okay to backfill. | |
| 07/09/2025 | ENGR - Drainage Structures | Not Ready | catch basin installation was delayed, not ready. | |
| 07/10/2025 | ENGR - Drainage Structures | Partial Pass | Catch basin to the southeast of building is installed correctly place and the 12 inch RCP is installed correctly out to the main parking lot driveway. Okay to backfill. | |
| 07/11/2025 | ENGR - Drainage Structures | Partial Pass | 2 catch basins and 47LF of 12" RCP on South-East corner are installed according to plans with proper slope. Okay to backfill. | |
| 07/15/2025 | ENGR - Drainage Structures | Partial Pass | Two catch basins at SE corner in main drive path, built to PAG 309, lowered east grate to achieve >2% apron slope and match the west basin's slope to the east basin. Okay to pour catch basin aprons. | |
| 07/16/2025 | ENGR - Drainage Structures | Partial Pass | Contractor poured one of the catch bases just the top on the east side the one on the west side I stopped in for pouring it because of the rain today | |
| 07/23/2025 | ENGR - Drainage Structures | Partial Pass | 7/23/25 Okay to pour Catch Basin 309. Unable to see Joint to Drainage pipe so do not backfill until we see it again after forms are stripped. Call us back out to reinspect. |
|
| 07/23/2025 | ENGR - Drainage Structures | Partial Pass | I informed the contractor they could pour the drainage basin, but before they backfill it and needs one more inspection | |
| 09/24/2025 | ENGR - Drainage Structures | Re-inspection required | 9/24/25 N side of project. Drain Pipe into Curb Catch Basin. 12" into 24" RCP Lateral joint correct per MAG STD DTL 525 type 1 Approx 40% elbow joint in 12" RCP needs 3rd hoop in middle and cross bars at 12" OC per MAG detail 505. Send me pictures of correct reinforcement per detail before completing collar. Now corrected. Ok to build collar. we will look at both when we come out. Wrong Catch Basin Was used in curb. It should be a PAG 307 Double CB per keynote in plan- currently a single in place. Do not back backfill this until Type of CB is resolved and we see correct joint in CB. Also electric lines are tucked under curb at CB. This needs to be resolved. As well. Call us back out for both joints. |
|
| 10/16/2025 | ENGR - Drainage Structures | Partial Pass | 10/16/25 Single catch basin in 307 noted ion 9/24/25 accepted by engineer RFI 0085. other catch basins to remain to plan. | |
| 10/31/2025 | ENGR - Drainage Structures | Partial Pass | 10/31/25 North side Next Catch Basin west of previous single is correct double 307 to plan. Storm Drain pipe invert is too high to bottom of CB. Clean out CB and Epoxy set two bars into floor. This will prevent displacement from hydraulic action. Place concrete up to invert. Low point of floor is storm drain invert. Send pictures of epoxy set bars. Okay to backfill. Shade correctly, Compact lifts to 95%. To the east 10” PVC Storm drain from Loading dock running 25’ N to main is correct to plan. Okay to connect to main. request inspection before backfilling. |
|
| 11/03/2025 | ENGR - Drainage Structures | Partial Pass | 11/3/25 The floor of PAG Double CB 307 is raised to the inverted of drain pipe by epoxy setting rebar into floor and pouring concrete to the invert. Okay to backfill, pour the Apron and curb on either side. Use expansion joint material at structure. 10" Drain pipe with Backflow preventer from the loading dock to Storm main connections good. Okay to backfill. Submit compaction reports. |