Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/10/2025
Applicant:
Andrew Venne
Description:
Interior Remodel

Permit Reviews

Permit Number - TC-COM-0625-01137
Permit Status: Complete
Permit Description: Interior Remodel
Start Date Submittal Complete Date Status  
12/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/26/2025 APPROVED Review Details
07/31/2025 RESTAMP - COMMERCIAL v.1 07/31/2025 APPROVED Review Details
12/09/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/11/2025 REQUIRES RESUBMIT Review Details
07/10/2025 COMMERCIAL REVIEW - FULL v.2 07/31/2025 APPROVED Review Details
06/12/2025 COMMERCIAL REVIEW - FULL v.1 07/02/2025 REQUIRES RESUBMIT Review Details
09/15/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/16/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0625-01137
Permit Status: Complete
Permit Description: Interior Remodel
Date Description Comments
06/27/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/29/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/27/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/12/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
07/29/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
06/27/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0625-01137
Permite Description: Interior Remodel
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
11/14/2025 COT - BULD - SWG Clearance N/A Not Applicable 11-14-25: not applicable
08/11/2025 COT - LCPL - Plumbing Final N/A Canceled Canceled per plumber. 8/11/2025
12/23/2025 COT - LCBU - Building Final N/A Partial Pass 12-23-25: submit letter that was requested for stem wall, pre slab, grout at loading dock walls. Submit as an attachment to the city- document must indicate that un-inspected items were completed per plans and meets or exceeds the 2018 IBC.
09/09/2025 COT - LCBU - Masonry Pregrout N/A Re-inspection required 9-9-25: arrived on site at approximately 1315 hours. CMU wall was already grouted so I was not able to verify reinforcement. Submit a letter to the city for review/approval documenting that reinforcement at dock wall was per approved plans & attach 3rd party inspection report to letter as well.
12/23/2025 COT - LCBU - Preslab N/A Partial Pass 12-23-25: submit letter that was requested for stem wall, pre slab, grout at loading dock walls. Submit as an attachment to the city- document must indicate that un-inspected items were completed per plans and meets or exceeds the 2018 IBC.
12/23/2025 COT - LCBU - Stem Wall/Retaining Wall N/A Partial Pass 12-23-25: submit letter that was requested for stem wall, pre slab, grout at loading dock walls. Submit as an attachment to the city- document must indicate that un-inspected items were completed per plans and meets or exceeds the 2018 IBC.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0625-01137
Permit Description: Interior Remodel
Total Completed Inspections - 19
Date Description Inspector Results Comments
08/12/2025 COT - HCPL - Rough Soil Passed 8-12-25: underground plumbing verified per plans. Okay to backfill with shading materials.
08/19/2025 COT - LCBU - Excavation/Rebar/Zoning Passed 8.19.25
APPROVED
09/17/2025 COT - LCBU - Framing Passed 9-17-25: framing inspection approved.
09/17/2025 COT - LCEL - Electrical Intermediate Passed 9-17-25: electrical intermediates approved. Okay to continue construction at progress areas.
10/09/2025 BULD - Electrical Clearance Passed 10/9/25: ECO TEP CLEARANCE FOR UNIT 151. VERBAL CLEARANCE 1:30pm
10/21/2025 COT - LCEL - Electrical Above Ceiling Passed 10-21-25: above ceiling junction boxes labeled, lights properly secured, and seismic wires in place. Mechanical properly secured/pookie joints approved. Okay to continue with TI.
11/14/2025 COT - LCEL - Grounding/Bonding Passed 11-14-25: approved.
11/14/2025 COT - LCEL - Electrical Final Passed 11-14-25: approved
11/18/2025 COT - FCON - Fire - Final Passed
11/18/2025 COT - FCON - Sprinkler - Final Passed
11/18/2025 COT - LCME - Mechanical Final Passed 11-18-25: mechanical final approved.
11/18/2025 COT - LCPL - Plumbing Final Passed 11-18-25: plumbing final approved.
12/09/2025 ENGR Engineering Final Passed
12/23/2025 TRSP - ROW - Final/Close-Out Passed Work was completed outside of the right of way
12/23/2025 COT - LCEL - Electrical Underground Passed 12-23-25: approved.
01/08/2026 COT - LCBU - Building Final Passed 1-8-26: Building Final Approved. All corrections made & 3rd party reports attached.
01/08/2026 COT - LCBU - Masonry Pregrout Passed 1-8-26: approved-3rd party report attached.
01/08/2026 COT - LCBU - Preslab Passed 1-8-26: approved-3rd party report attached.
01/08/2026 COT - LCBU - Stem Wall/Retaining Wall Passed 1-8-26: approved-3rd party report attached.