Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0625-01137
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/12/2025 Commercial Electrical Standard APPROVED
07/01/2025 Site Engineering Standard APPROVED
07/02/2025 Site Zoning Standard APPROVED
07/02/2025 Water - PDSD Standard APPROVED
06/12/2025 Outdoor Lighting Standard NOT REQUIRED No modifications to the outdoor lighting.
07/02/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
06/27/2025 Commercial Building Standard REQUIRES RESUBMIT Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Additionally, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed.
1. Please provide existing Floor/Demolition plans with your next submittal. IBC 107.2.1
2. Please reconfigure the Warehouse bathroom to be accessible. For example, the required clearance around a water closet shall be 60 inches (1525 mm) minimum in width, measured perpendicularly from the sidewall. 2009 ICC A117.1 604.3.1
3. Please amend plans t provide an accessible service counter height and width for selected approach. IBC Chapter 11
4. Please amend the plans so the drinking fountains are not protruding objects and either cane detectable or otherwise compliant. IBC 1003.3
3. Sheet A3: Please provide the occupancy, number of occupants and occupant load factor for each space or room for the Office Floor Plan. IBC 107.2.3 & IBC 1004.5
4. Please amend the plans to provide a project specific statement of sections on the plan set to show the special inspections and testing required for this project. IBC 1704, IBC 1705.
Please contact me if you have any questions about these comments.
Mark Masek
Plans Examiner – Building Safety
Planning and Development Services | City of Tucson
main 520.837.4994
email mark.masek@tucsonaz.gov
07/02/2025 Commercial Mechanical Standard REQUIRES RESUBMIT 1. Fan coils FC-1 and FC-2 have return air grilles co-located in the show room. Provide smoke detectors in the return air ducts, upstream of any outside air connections, for all FC-1 and FC-2. Reference: Section 606.2.2, IMC 2018.
2. The System Design Report shows a sensible oil load of 89.7 MBH for the office area but the Heat Pump Split System Schedule provides a total sensible cooling capacity of 133.8 MBH. Provide justification for installing HVAC units having a total cooling capacity that exceeds the total cooling load shown in the submitted calculations. Reference: Section C403.3.1, IECC 2018.
07/02/2025 Commercial Plumbing Standard REQUIRES RESUBMIT 1. Revise the cleanouts for partial waste isometric A/P3 to provide cleanouts for all horizontal drains that are sized per Section 708.1.7, IPC 2018 (e.g. the 4” and 3” horizontal drains). Reference: Sections 708.1.1 and 708.1.8, IPC 2018.
2. Provide access to the shut off valve and check valve for the two loading dock sump pumps (i.e. locate the valves outside of the sump). Reference: Section 712.2, IPC 2018.
3. Detail 211 calls for a 5/8” force main to transition to a ¾” condensate drain in the ceiling space. Show how this transition is to be made. Reference: Section 712.3.5, IPC 2018.
06/12/2025 Fire New Construction Standard REVIEW COMPLETED
06/12/2025 PDSD Application Completeness Express REVIEW COMPLETED