Permit: TC-COM-0625-01114
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4697 S CAMPBELL AV
Address NEW:
4697 S CAMPBELL AV
Apply Date:
06/06/2025
Applicant:
Austin Hodges
Description:
New construction bank and associated site work
Permit Reviews
Permit Number - TC-COM-0625-01114
Permit Status: Complete
Permit Description: New construction bank and associated site work
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/15/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/17/2026 | APPROVED |
| 12/03/2025 | ADMINISTRATIVE v.2 | 12/03/2025 | REQUIRES RESUBMIT |
| 07/23/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/14/2025 | REQUIRES RESUBMIT |
| 12/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/30/2025 | APPROVED |
| 06/30/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/02/2026 | APPROVED |
| 06/06/2025 | COMMERCIAL REVIEW - FULL v.1 | 07/01/2025 | REQUIRES RESUBMIT |
| 12/08/2025 | ADMINISTRATIVE v.3 | 12/09/2025 | APPROVED |
| 07/07/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/10/2026 | APPROVED |
| 09/03/2025 | COMMERCIAL REVIEW - FULL v.4 | 09/25/2025 | REQUIRES RESUBMIT |
| 01/13/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/16/2026 | APPROVED |
| 12/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/10/2025 | REQUIRES RESUBMIT |
| 07/21/2025 | COMMERCIAL REVIEW - FULL v.2 | 07/21/2025 | REQUIRES RESUBMIT |
| 11/17/2025 | COMMERCIAL REVIEW - FULL v.5 | 11/21/2025 | APPROVED |
| 11/21/2025 | RESTAMP - COMMERCIAL v.1 | 11/26/2025 | APPROVED |
| 11/26/2025 | ADMINISTRATIVE v.1 | 11/26/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0625-01114
Permit Status: Complete
Permit Description: New construction bank and associated site work
| Date | Description | Comments |
|---|---|---|
| 07/02/2026 | AIR BALANCING REPORT IS REQUIRED. | |
| 06/06/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/13/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 06/13/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 06/13/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 06/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 07/02/2026 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 06/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 06/13/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 01/14/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 07/02/2026 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0625-01114
Permite Description: New construction bank and associated site work
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 1-30-26: excavation/reinforcement for stem wall footings verified per S4, schedule C1, F1, and details located on page S6/details 101-106. Okay for concrete placement at progress areas. |
| 02/12/2026 | COT - HCBU - Preslab | N/A | Partial Pass | 2-12-26: reinforcement for preslab at slab on grade verified per S.4 slab notes 1&2, reinforcement for turndown verified per S.6 Details 101, 104, 105. Okay for concrete placement. |
| 04/03/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 4-3-26: add 10 mil tape to copper line making contact with above ceiling duct at lounge, add Boca plates to marked locations-protection of plastic DWV requires a plate that extends 2" above & below top plates. Okay to insulate exterior walls and will check for corrections at next inspection. |
| 04/01/2026 | COT - HCPL - Plumbing Intermediate | N/A | Re-inspection required | 4-1-26: add supports to DWV at 4' intervals, fire foam all penetrations at top plates and where DWV penetrates exterior walls, add supports to horizontal copper lines at 6' maximum, copper lines 3/4" and larger must be insulated with R3 insulation, add Boca plates to domestic lines and DWV where closer than 1 1/4" from edge of studs. |
| 04/01/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 4-1-26: with the exception of a few penetrations at the top plates; in wall electrical approved. Will verify sealing of penetrations prior to insulation. Note: pending above ceiling electrical inspection. |
| 06/09/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 6-9-26: seal all penetrations at cash room, seal low voltage penetration at top plate of access teller room. |
| 02/19/2026 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 2-19-26: verified 3' trench depth with a 2" water copper line with tracer wire on an approximate 85' run. Copper line stubs up approximately 12' away from Tucson Water's main line & 2" copper line transitions to 1.5" into building. 2" verified under test at 85psi-okay to backfill progress areas using shading materials. |
| 03/04/2026 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 3-4-26: verified trench depth at 3' on a total of 9-1" conduits for exterior light poles, 1-2" conduit for camera and 1" conduit for monument. Okay to backfill progress areas. |
| 04/01/2026 | COT - HCPL - Plumbing Roof Drains | N/A | Partial Pass | 4-1-26: in wall domestic and DWV verified under test. |
| 07/08/2026 | ENGR Engineering Final | N/A | Partial Pass | Site work is finished between the building and the parking lot and drive through. Contractor needs a little more time to finish on other side of drive-through and parking lot. Keep all potentially dangerous equipment and or construction materials away from public behind fencing. Keep public and business employees separated from construction activities. Correct address numbers need to be on building. These need to be elevated facing Campbell. Contingent on these conditions being met Okay to apply for level two TCO. |
| 07/06/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok for Level 4 TCO. Need 15 inch exterior building address numbers on Campbell side of building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0625-01114
Permit Description: New construction bank and associated site work
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2026 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | ||
| 02/05/2026 | COT - HCPL - Rough Soil | Passed | Underground plumbing in slab approved. Okay to backfill. Shading materials are required. 2/5/2026 | |
| 02/13/2026 | COT - HCPL - Sewer | Passed | Passed 2/13/26, ok to backfill | |
| 03/12/2026 | COT - HCBU - Roof Nailing | Passed | 3-12-26: roof nailing and nailing at the parapets approved. Okay to dry in roof. | |
| 03/16/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 03/16/2026 | COT - HCBU - Framing | Passed | ||
| 05/13/2026 | BULD - Electrical Clearance | Passed | 5/13/26 TEP CLEARANCE: ECO |
|
| 06/09/2026 | COT - HCEL - Electrical Above Ceiling | Passed | 6-9-26: electrical above ceiling approved. | |
| 06/25/2026 | COT - BULD - SWG Clearance | Passed | phoned in to Jennifer at 12:41 PM. | |
| 06/25/2026 | COT - HCEL - Electrical Progress | Passed | 6-25-26: Clearance to reconnect service after moving TEP transformer. Phoned in to Jennifer at 12:41 PM. | |
| 07/02/2026 | COT - HCBU - Building Progress | Passed | 7-2-26: roof drains previously inspected & approved on 4/1/26. | |
| 07/02/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 7-2-26: previously inspected & approved. | |
| 07/02/2026 | COT - HCBU - Preslab | Passed | 7-2-26: preslab approved. | |
| 07/02/2026 | COT - HCPL - Plumbing Progress | Passed | 7-2-26: approved. | |
| 07/02/2026 | COT - HCPL - Plumbing Intermediate | Passed | 7-2-26: plumbing intermediates approved. | |
| 07/02/2026 | COT - HCME - Mechanical Progress | Passed | 7-2-26: mechanical intermediates approved. | |
| 07/02/2026 | COT - HCME - Mechanical Intermediate | Passed | 7-2-26: mechanical intermediates approved. | |
| 07/02/2026 | COT - HCEL - Electrical Intermediate | Passed | 7-2-26: electrical intermediates approved. | |
| 07/02/2026 | COT - HCME - Mechanical Above Ceiling | Passed | 7-2-26: mechanical above ceiling. | |
| 07/02/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | 7-2-26: plumbing above ceiling approved. | |
| 07/02/2026 | COT - HCPL - Yard Water Line | Passed | 7-2-26: previously inspected & approved. | |
| 07/02/2026 | COT - HCEL - Electrical Underground | Passed | 7-2-26: approved. | |
| 07/02/2026 | COT - HCPL - Plumbing Roof Drains | Passed | 7-2-26: previously inspected & approved on 4/1/26. | |
| 07/02/2026 | COT - HCEL - Grounding/Bonding | Passed | 7-2-26: grounding/bonding approved. | |
| 07/06/2026 | COT - FCON - Alarm - Final | Passed | ||
| 07/07/2026 | COT - HCBU - Building Above Ceiling | Passed | ||
| 07/07/2026 | COT - HCEL - Outdoor Lighting | Passed | ||
| 07/08/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 07/15/2026 | COT - HCEL - Electrical Final | Passed | 7-15-26: electrical final approved. | |
| 07/15/2026 | COT - HCME - Mechanical Final | Passed | 7-15-26: mechanical final approved. | |
| 07/15/2026 | COT - HCPL - Plumbing Final | Passed | 7-15-26: plumbing final approved. | |
| 07/15/2026 | COT - HCBU - Building Final | Passed | 7-15-26: Building final approved. | |
| 07/15/2026 | ENGR Engineering Final | Passed | ||
| 07/15/2026 | COT - FCON - Fire - Final | Passed | ||
| 07/15/2026 | PDSD Building Division - Demo - Utilities | Passed | 7-15-26: approved. | |
| 07/16/2026 | COT - HCBU - CofO | Passed |