Permit: TC-COM-0525-00955
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
6950 S COUNTRY CLUB RD
Address NEW:
6950 S COUNTRY CLUB RD
Apply Date:
05/09/2025
Applicant:
Andrew Christopher
Description:
Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
Permit Reviews
Permit Number - TC-COM-0525-00955
Permit Status: Needs resubmittal
Permit Description: Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/03/2025 | COMMERCIAL REVIEW - FULL v.2 | 07/29/2025 | REQUIRES RESUBMIT |
| 08/20/2025 | COMMERCIAL REVIEW - FULL v.4 | 08/25/2025 | APPROVED |
| 01/14/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/20/2026 | REQUIRES RESUBMIT |
| 01/08/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/12/2026 | APPROVED |
| 12/09/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/12/2025 | APPROVED |
| 08/01/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/19/2025 | REQUIRES RESUBMIT |
| 05/14/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/10/2025 | REQUIRES RESUBMIT |
| 08/25/2025 | RESTAMP - COMMERCIAL v.1 | 08/27/2025 | APPROVED |
| 12/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/09/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0525-00955
Permit Status: Needs resubmittal
Permit Description: Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/19/2025 | ***NOTE: The RTO2 mechanical equipment on a separate permit must be installed/pass inspection prior to the issuance of the Certificate of Occupancy. |
Conditions
Permit Number - TC-COM-0525-00955
Permit Status: Needs resubmittal
Permit Description: Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
| Date | Description | Comments |
|---|---|---|
| 05/14/2025 | There are two addresses associated with this location 6950 S COUNTRY CLUB RD TUCSON, AZ 85756 & 6950 S COUNTRY CLUB RD UNIT 304 TUCSON, AZ 85756. Please confirm the address for this permit application. | |
| 12/04/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 05/14/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0525-00955
Permite Description: Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 12-4-25: mechanical intermediate-fix tear to flex at room 117, label junction boxes at column located in front room 117, add seismic wires throughout at room's 115, 116, 117, 118, 119-add tape to flex at connection point of trunk. Reinspection required- schedule when ready. |
| 12/04/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 12-4-25: provide hood specifications- upload specs. as an attachment to the city for review. |
| 12/23/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 12-23-25: not applicable. |
| 12/04/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 12-4-25: mechanical intermediate-fix tear to flex at room 117, label junction boxes at column located in front room 117, add seismic wires throughout at room's 115, 116, 117, 118, 119-add tape to flex at connection point of trunk. Reinspection required- schedule when ready. |
| 12/04/2025 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 12-4-25: mechanical intermediate-fix tear to flex at room 117, label junction boxes at column located in front room 117, add seismic wires throughout at room's 115, 116, 117, 118, 119-add tape to flex at connection point of trunk. Reinspection required- schedule when ready. |
| 12/23/2025 | COT - HCBU - Building Final | N/A | Partial Pass | 12-23-25: This permitTCCOM 0525-0079 must be completed prior to issuing a Cof O. |
| 12/04/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 12-4-25: provide hood specifications- upload specs. as an attachment to the city for review. |
| 01/06/2026 | COT - HCBU - TCO | N/A | Partial Pass | 1-6-26: okay for a Level 1 TCO. Pending Fire inspection & see notes from building final. |
| 12/18/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Everything passed just need a knox box and facp sign. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0525-00955
Permit Description: Manufacturing floor tenant improvement (NOTE: C of O cannot be issued until the RTO2 mechanical equipment is installed and passed inspection via a separate permit.)
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2025 | COT - HCBU - Building Progress | Passed | 12-4-25: approved. | |
| 12/04/2025 | COT - HCBU - Framing | Passed | 12-4-25: framing at mezzanine approved. | |
| 12/04/2025 | COT - HCPL - Plumbing Progress | Passed | 12-4-25: approved. | |
| 12/18/2025 | COT - FCON - Alarm - Final | Passed | ||
| 12/18/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 12/23/2025 | COT - HCME - Mechanical Final | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCME - Mechanical Intermediate | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCME - Mechanical Progress | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCPL - Plumbing Final | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCEL - Electrical Progress | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCBU - Building Above Ceiling | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCPL - Plumbing Intermediate | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCEL - Electrical Final | Passed | 12-23-25: approved. | |
| 12/23/2025 | COT - HCEL - Electrical Intermediate | Passed | 12-23-25: approved. | |
| 12/29/2025 | ENGR Engineering Final | Passed | Exterior is complete, all egress doors are uninhibited. | |
| 01/05/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 01/06/2026 | COT - HCBU - Building Final | Passed | 1-6-26: building final approved. Submit water chlorination report together with elevator certificate to the city for review. Also, address pending condition with regard to installation of RTO-Submit a letter from the architect or engineer of record stating that RTO will be installed on a new unrelated permit. |
|
| 01/06/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | 1-6-26: approved. | |
| 01/08/2026 | COT - FCON - Fire - Final | Passed |