Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 09/17/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
9-17-25: plumbing progress at room's 107, 108, 109, & 110 verified per plans. Okay to continue construction at progress areas. |
| 09/29/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
9-29-25: in wall domestic and DWV at mezzanine verified per plans and under test. Okay to continue with TI at progress areas. |
| 12/04/2025 |
COT - HCPL - Plumbing Progress |
|
Passed |
12-4-25: approved. |