Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 09/17/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
9-17-25: electrical above ceiling room's 107, 108, 109, & 110 verified per plans. Okay to continue construction at progress areas. |
| 12/04/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
12-4-25: mechanical intermediate-fix tear to flex at room 117, label junction boxes at column located in front room 117, add seismic wires throughout at room's 115, 116, 117, 118, 119-add tape to flex at connection point of trunk. Reinspection required- schedule when ready. |
| 12/08/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
12/8/2025 Rooms 115,116,117,118,119 (mezzanine) approved. Okay for ceiling tiles to be placed. |
| 12/15/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
12-15-25: electrical above ceiling in rm. 104 approved. |
| 12/23/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Passed |
12-23-25: approved. |