Permit: TC-COM-0323-00868
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
5590 E TRAVEL PLAZA WY
Address NEW:
5590 E TRAVEL PLAZA WY
Apply Date:
03/23/2023
Applicant:
Charmalee Jayawardena
Description:
NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
Permit Reviews
Permit Number - TC-COM-0323-00868
Permit Status: Issued
Permit Description: NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/21/2023 | REQUIRES RESUBMIT |
| 12/06/2023 | RESTAMP - COMMERCIAL v.1 | 12/07/2023 | APPROVED |
| 06/05/2025 | RESTAMP - COMMERCIAL v.1 | 06/06/2025 | APPROVED |
| 03/26/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/01/2025 | APPROVED |
| 08/27/2026 | SPECIAL INSPECTION REVIEW v.1 | 08/28/2026 | APPROVED |
| 07/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/01/2025 | APPROVED |
| 09/02/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | N/A | APPROVED |
| 11/27/2023 | COMMERCIAL REVIEW - FULL v.3 | 12/06/2023 | APPROVED |
| 11/20/2025 | COMMERCIAL REVIEW - FULL v.3 | 12/12/2025 | APPROVED |
| 08/12/2026 | RESTAMP - COMMERCIAL v.1 | 08/18/2026 | APPROVED |
| 05/01/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 05/23/2025 | REQUIRES RESUBMIT |
| 03/24/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/21/2023 | REQUIRES RESUBMIT |
| 09/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/29/2025 | REQUIRES RESUBMIT |
| 07/24/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/16/2023 | REQUIRES RESUBMIT |
| 09/25/2025 | COMMERCIAL REVIEW - FULL v.2 | 09/26/2025 | REQUIRES RESUBMIT |
| 06/05/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 06/05/2025 | APPROVED |
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/22/2023 | REQUIRES RESUBMIT |
| 08/07/2025 | COMMERCIAL REVIEW - FULL v.1 | 08/27/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0323-00868
Permit Status: Issued
Permit Description: NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 11/13/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/13/2023 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 11/13/2023 | Stair Designs must be submitted and approved prior to... |
Conditions
Permit Number - TC-COM-0323-00868
Permit Status: Issued
Permit Description: NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
| Date | Description | Comments |
|---|---|---|
| 11/13/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 07/28/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/06/2025 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 11/13/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 08/28/2026 | Prior to Final - Special Inspections - SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 11/13/2023 | Please submit a separate sign permit for an signs associated with this projet. | |
| 07/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 02/05/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 11/13/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0323-00868
Permite Description: NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2025 | COT - HCPL - Rough Soil | N/A | Re-inspection required | 11-26-25: city approved plans not on site-Reschedule inspection. |
| 12/10/2025 | COT - HCPL - Sewer | N/A | Not Ready | Courtesy inspection. 12/10/2025 |
| 12/19/2025 | COT - HCBU - Preslab | N/A | Re-inspection required | 12/19/25: reinforcement at (3)interior spread footings must maintain 3" clearance from earth, all plumbing at slab must be wrapped to protect from concrete. |
| 05/28/2026 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 5-28-26: main water line verified under test at 80psi. Okay to backfill using shading materials. |
| 08/26/2026 | ENGR Engineering Final | N/A | Partial Pass | Site is complete except: -Handicap ramp that accesses landscaped area on west side of site is being rebuilt so it complies. - Section of asphalt patch over utility trench that settled on NE side of building. Okay to apply for TCO level 4 while these 2 repairs are completed. These 2 areas need to be cordoned off sufficiently with safety barrier during repair and access cannot be compromised. -Outstanding conditions need to be satisfied pending Final. |
| 08/31/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 8/31/26: OKAY TO REQUEST LEVEL 4 TCO. PENDING CONDITIONS |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0323-00868
Permit Description: NEW TRUCK TIRE AND LIGHT MECHANICAL MAINTENANCE FACILITY
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 10/24/25 Corrections made on the corners. |
|
| 12/02/2025 | COT - HCPL - Rough Soil | Passed | 12-2-25: underground plumbing verified under test and per plans. Okay to backfill with shading materials. | |
| 03/31/2026 | COT - HCPL - Gas Pressure Test | Passed | 3-31-26: gas pressure test approved. | |
| 05/19/2026 | COT - HCPL - Sewer | Passed | 5-19-26: final section of SDR35 PVC sewer pipe verified under test. Okay to backfill approximately 70' of open trench. | |
| 07/30/2026 | BULD - Electrical Clearance | Passed | 7-30-26: okay to meter/energize system. ECO clearance issued to TEP. | |
| 08/20/2026 | COT - HCPL - Plumbing Final | Passed | ||
| 08/20/2026 | COT - HCEL - Electrical Final | Passed | ||
| 08/20/2026 | COT - HCBU - Framing | Passed | ||
| 08/20/2026 | COT - HCBU - Preslab | Passed | ||
| 08/20/2026 | COT - HCEL - Electrical Intermediate | Passed | ||
| 08/25/2026 | COT - HCPL - Backwater Valve | Passed | ||
| 08/25/2026 | COT - HCEL - Grounding/Bonding | Passed | ||
| 08/25/2026 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | ||
| 08/25/2026 | COT - HCPL - Yard Water Line | Passed | 8-25-26: main water line approved. | |
| 08/25/2026 | COT - HCPL - Gas Final | Passed | 8-25-26: approved. | |
| 08/25/2026 | COT - HCME - Venting | Passed | 8-25-26: venting approved. | |
| 08/25/2026 | COT - HCEL - Electrical Underground | Passed | ||
| 08/26/2026 | COT - FCON - Fire - Final | Passed | Per chris basadua this inspection passed the previous day. | |
| 08/31/2026 | TRSP - ROW - Final/Close-Out | Passed | Job site is new building structure on private property with no impact to right of way, approved | |
| 08/31/2026 | COT - HCME - Mechanical Final | Passed |