Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
08/26/2026 ENGR Engineering Final Partial Pass Site is complete except:
-Handicap ramp that accesses landscaped area on west side of site is being rebuilt so it complies.
- Section of asphalt patch over utility trench that settled on NE side of building.
Okay to apply for TCO level 4 while these 2 repairs are completed. These 2 areas need to be cordoned off sufficiently with safety barrier during repair and access cannot be compromised.
-Outstanding conditions need to be satisfied pending Final.