Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
03/31/2026 COT - HCBU - Framing Partial Pass 3-31-26: metal interior framing for room's 101, 102, 103, 104, 105, 106 and north/south demising walls approved. Okay to one side and schedule a drywall screw inspection prior to tape & texture.
04/14/2026 COT - HCBU - Framing Partial Pass 4-14-26: 1st layer at interior drywall screws at walls at warehouse to include, restrooms, waiting room approved. Drywall screws at South Exterior wall-2nd layer approved.
04/16/2026 COT - HCBU - Framing Partial Pass 4-16-26: second layer of 5/8" drywall screws at north exterior/interior walls of warehouse approved. Okay to add 3rd layer of drywall at progress areas.
04/20/2026 COT - HCBU - Framing Re-inspection required 4-20-26: missing screws at exterior/interior walls together with sections of drywall. Fire caulk all penetrations at firewalls. Reschedule when ready.
04/21/2026 COT - HCBU - Framing Partial Pass 4-21-26: 3rd layer of 5/8" drywall at north interior & exterior walls of warehouse approved-Okay to tape & texture. 2nd layer of 5/8" drywall at Interior south wall is okay for 3rd layer. South exterior wall of warehouse is okay to tape & texture 3rd layer.
04/27/2026 COT - HCBU - Framing Partial Pass 4-27-26: 3rd layer of drywall screws at interior warehouse wall together with lobby approved for tape & texture.
05/18/2026 COT - HCBU - Framing Partial Pass 5/18/2026 partial pass. T bar inspection approved office spaces and bathroom along with hallway.
06/02/2026 COT - HCBU - Framing Partial Pass 6-2-26: HVAC/mechanical rough in at offices & restrooms approved. Okay to install ceiling tiles at progress areas . Also, inspected Air line pressure at 85psi.
08/20/2026 COT - HCBU - Framing Passed