Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 03/05/2026 |
COT - HCPL - Sewer |
|
Re-inspection required |
3-5-26: okay to shade grease/water separator but reschedule inspection when under test. |
| 03/06/2026 |
COT - HCPL - Sewer |
|
Partial Pass |
3-6-26: grease/water separator verified under test. Okay to continue with backfill using shading materials. |
| 04/10/2026 |
COT - HCPL - Sewer |
|
Partial Pass |
4-10-26: SDR35 pvc sewer line verified under- Okay to backfill approximately 75' of trench using shading materials. |
| 04/30/2026 |
COT - HCPL - Sewer |
|
Partial Pass |
4-30-26: approximately 90' of SDR35 PVC stemming from northeast quad and extending west to clean out was verified per plans & under test. Okay to backfill progress areas using shading materials. |
| 05/05/2026 |
COT - HCPL - Sewer |
|
Partial Pass |
5-5-26: approximately 220' of 4" SDR35 PVC stemming from east to west approved. Okay to backfill progress areas using shading materials. Section to be verified under test at a later date. |
| 05/19/2026 |
COT - HCPL - Sewer |
|
Passed |
5-19-26: final section of SDR35 PVC sewer pipe verified under test. Okay to backfill approximately 70' of open trench. |
| 12/10/2025 |
COT - HCPL - Sewer |
|
Not Ready |
Courtesy inspection. 12/10/2025 |