Permit: TC-COM-0125-00139
Permit Details
Status:
In Review
Type:
Commercial Building
Address:
10096 E OLD VAIL RD
Address NEW:
10096 E OLD VAIL RD
Apply Date:
01/21/2025
Applicant:
Carrie Murphy
Description:
New Valvoline - minor auto service building REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry. Add Timeclock to EF-1.
Permit Reviews
Permit Number - TC-COM-0125-00139
Permit Status: In review
Permit Description: New Valvoline - minor auto service building
REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry.
Add Timeclock to EF-1.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/27/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 05/11/2026 | REQUIRES RESUBMIT |
| 04/24/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/19/2025 | APPROVED |
| 05/19/2025 | RESTAMP - COMMERCIAL v.1 | 05/21/2025 | APPROVED |
| 05/11/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 05/13/2026 | APPROVED |
| 03/18/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/15/2025 | REQUIRES RESUBMIT |
| 01/29/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/20/2025 | REQUIRES RESUBMIT |
| 05/20/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | N/A | IN REVIEW |
Outstanding Activity Conditions
Permit Number - TC-COM-0125-00139
Permit Status: In review
Permit Description: New Valvoline - minor auto service building
REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry.
Add Timeclock to EF-1.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 02/18/2025 | SPECIAL INSPECTION OF COLD-FORMED STEEL DECK IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OF CONCRETE CONSTRUCTION IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OR STEEL CONSTRUCTION IS REQUIRED. |
| 02/19/2025 | PREFABRICATED WOOD TRUSSES- DESIGN PLANS MUST BE SUBMITTED AND APPROVED PRIOR TO FINAL INSPECTIONS. PLEASE SUBMIT TO STRUCTURAL ENGINEER FOR APPROVAL AND REVIEW STAMP PRIOR TO SUBMITTING TO THE CITY OF TUCSON |
Conditions
Permit Number - TC-COM-0125-00139
Permit Status: In review
Permit Description: New Valvoline - minor auto service building
REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry.
Add Timeclock to EF-1.
| Date | Description | Comments |
|---|---|---|
| 04/14/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 01/29/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/06/2025 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 02/19/2025 | Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Pima County Industrial Wastewater Review Required - Kelsey.McMonagle@pima.gov or Adam.DeLaTorre@pima.gov for review and assessment of the proposed oil separator.. | |
| 01/29/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/05/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: In Review
Permit Number: TC-COM-0125-00139
Permite Description: New Valvoline - minor auto service building
REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry.
Add Timeclock to EF-1.
Total Outstanding Inspections - 15
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2025 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | 8-28-25: reinforcement verified per plans-okay to pour pit walls . |
| 08/20/2025 | COT - LCPL - Sewer | N/A | Partial Pass | Partial pass. From sewer tie in up to building on test along with tracer wire and tape. Okay to backfill progress areas. Shading required. Pending tie into building. 8/20/2025 |
| 12/17/2025 | COT - HCPL - Backwater Valve | N/A | Partial Pass | 12-17-25: on site plumber requested that 1 1/4" domestic pvc main water line be relooked at under test. I verified system under test and explained that this inspection had previously been approved back on 10/25. Okay to continue with construction at progress areas. |
| 09/08/2025 | COT - LCBU - Preslab | N/A | Not Ready | 9-8-25: Arrived at location at approximately 1215 hours and spoke with a worker who indicated he had nothing for me to inspect today. Left site at 1225-reschedule when ready. |
| 04/03/2026 | BULD - Electrical Clearance | N/A | Re-inspection required | 4-3-26: missing grounding rods, metallic address label, rubber/plastic bushings at ct can & disconnects, and feeders must be pulled in. Also, submit revision regarding conduit change to the city for review & provide torque report-see previous notes for information. |
| 09/16/2025 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | 9-16-25: canceled by contractor. |
| 05/13/2026 | COT - LCBU - Building Final | N/A | Re-inspection required (with fee) | 5-13-26: missing receptacle cover at upstairs closet, add plastic bushings to jumper junction box located between subpanels, add plastic bushings to low voltage at overhead bay door motors & install low voltage in mc cabling, label junction boxes throughout, missing cover lids on low voltage junction boxes& labeling throughout, open knockouts at junction boxes downstairs, adjust restroom door to 5 pounds of pressure, install labeling on disconnects-per NEC, labeling must be able to withstand the elements, label all emergency disconnects-per NEC, 230.85 (E)(2), the lettering must be 1/2" minimum and must identify the purpose and the circuit, complete installation of sum pump, install cover plates at office, complete labeling of all receptacles. See previous notes regarding a RFI on pour back at electrical room. Have architect submit a revision to the city for review documenting details. See previous failed inspections for roof, underground electrical and all pending inspections. It appears that the roof was never inspected prior to it being covered. If you have videos/pictures that can clearly show the nailing was done per plans and meets the 2018 IBC, then please upload them onto the city portal for review and show such items to the inspector at the next inspection. Stopped inspection- additional items may be noted. |
| 04/20/2026 | COT - LCEL - Electrical Final | N/A | Partial Pass | |
| 08/28/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 8-28-25: verified 1-1" Schedule 40 conduit with 1/0 copper attached to reinforcement. Okay to pour. |
| 05/11/2026 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | 5-11-26: label all junction boxes, label disconnects, add plastic bushings at sub panels/ and at electrical gutters, add plates to secure wiring at rolling doors, update panel schedules, secure mini split, provide a letter for "fix" or possible pour back opening at grade inside of electrical room, open knockout at downstairs south wall junction box, missing receptacle cover at mechanical room, adjust door pressure to 5 pounds of pressure, install ADA restroom sign, complete installation of pump near condensers, install cover plates on low voltage. Stopped inspection-additional items may be noted. |
| 05/19/2026 | COT - LCEL - Outdoor Lighting | N/A | Re-inspection required | 5-19-26: provide specification sheets and a ladder to verify outdoor lighting. |
| 12/02/2025 | COT - LCBU - Roof Nailing | N/A | Re-inspection required | 12-2-25: called point of contact at 1155 hours but received no answer. Arrived on site and waited over 12-2-25: electrical above ceiling approved. Okay to continue with TI.0 minutes for contractor. Left at 1216 hours-reschedule inspection. |
| 05/19/2026 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | 5-19-26: not applicable. |
| 05/19/2026 | ENGR Engineering Final | N/A | Re-inspection required | Address # needs to face Old Vail Rd. |
| 05/11/2026 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 5-11-26: label all junction boxes, label disconnects, add plastic bushings at sub panels/ and at electrical gutters, add plates to secure wiring at rolling doors, update panel schedules, secure mini split, provide a letter for "fix" or possible pour back opening at grade inside of electrical room, open knockout at downstairs south wall junction box, missing receptacle cover at mechanical room, adjust door pressure to 5 pounds of pressure, install ADA restroom sign, complete installation of pump near condensers, install cover plates on low voltage. Stopped inspection-additional items may be noted. |
Completed Inspections
Permit Status: In Review
Permit Number: TC-COM-0125-00139
Permit Description: New Valvoline - minor auto service building
REV1: Revised electrical to coordinate conduit sizes with contractor installed conduits. Relocation of streetlight to coordinate with drive entry.
Add Timeclock to EF-1.
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2025 | PDSD Building Division Pre-Construction Meeting | Passed | ||
| 10/03/2025 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 10/03/2025 | COT - LCPL - Rough Soil | Passed | ||
| 10/03/2025 | COT - LCPL - Yard Water Line | Passed | ||
| 10/03/2025 | COT - LCPL - Sewer | Passed | ||
| 10/29/2025 | COT - LCBU - Framing | Passed | Passed 10/29/25 ok to proceed | |
| 12/09/2025 | COT - LCME - Mechanical Intermediate | Passed | 12.9.25 Approved for partial pass upper level only. Proceed |
|
| 12/24/2025 | COT - LCEL - Electrical Intermediate | Passed | Passed 12/24/25 | |
| 01/13/2026 | COT - LCBU - Preslab | Passed | Trash enclosure | |
| 01/13/2026 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 03/23/2026 | PDSD Building Division SIte Consultation | Passed | ||
| 04/17/2026 | COT - LCEL - Grounding/Bonding | Passed | ||
| 04/17/2026 | BULD - Electrical Clearance | Passed | 4/16/26 TEP CLEARANCE: ECO |
|
| 05/04/2026 | COT - LCPL - Plumbing Intermediate | Passed | 5-4-26: plumbing intermediates approved. | |
| 05/11/2026 | COT - FCON - Fire - Final | Passed | ||
| 05/15/2026 | COT - LCEL - Electrical Underground | Passed | 5-15-26: approved. | |
| 05/15/2026 | COT - LCPL - Plumbing Final | Passed | 5-15-26: plumbing final approved. Okay for a Level 1 TCO. | |
| 05/19/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 5-19-26: approved. | |
| 05/19/2026 | TRSP - ROW - Final/Close-Out | Passed | no impact to RoW, approved |