Permit: T22CM06798
Permit Details
Apply Date:
09/02/2022
Applicant:
Gabe Lara
Description:
New Storage Facility
Permit Reviews
Permit Number - T22CM06798
Permit Status: Complete
Permit Description: New Storage Facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/02/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/04/2022 | COMPLETED |
| 03/29/2023 | COMMERCIAL REVIEW - FULL v.5 | 04/18/2023 | APPROVED |
| 02/01/2023 | COMMERCIAL REVIEW - FULL v.3 | 02/17/2023 | REQUIRES RESUBMIT |
| 03/20/2024 | COMMERCIAL REVIEW - FULL v.2 | 03/21/2024 | REQUIRES RESUBMIT |
| 04/18/2023 | RESTAMP - COMMERCIAL v.1 | 04/18/2023 | APPROVED |
| 05/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/12/2023 | REQUIRES RESUBMIT |
| 11/21/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/22/2022 | REQUIRES RESUBMIT |
| 11/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/13/2023 | APPROVED |
| 05/12/2023 | RESTAMP - COMMERCIAL v.1 | 05/12/2023 | APPROVED |
| 08/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/11/2023 | REQUIRES RESUBMIT |
| 09/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/14/2023 | APPROVED |
| 03/21/2024 | COMMERCIAL REVIEW - FULL v.3 | 03/21/2024 | APPROVED |
| 05/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 05/12/2023 | APPROVED |
| 02/18/2023 | COMMERCIAL REVIEW - FULL v.4 | 03/17/2023 | REQUIRES RESUBMIT |
| 12/14/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/11/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM06798
Permit Status: Complete
Permit Description: New Storage Facility
| Date | Description | Comments |
|---|---|---|
| 03/11/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 05/03/2023 | Pre-Engineered Metal Building Designs must be submitted and approved prior to ... | |
| 03/11/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 03/11/2023 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 03/14/2023 | Prior to project being finalized applicant must provide DO NOT ISSUE C of O UNTIL RECORDED DOCUMENTS FOR THE ABANDONEMENT OF 10’ COMM. ESMT & PROPOSED NEW PUBLIC EASEMENT ARE PROVIDED FOR DP22-0219. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06798
Permite Description: New Storage Facility
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/22/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 8/22/2023 from main CT can 15' stubbed out into fire riser room for pump. Dock leveler to into the room for control. |
| 08/22/2023 | COT - HCBU - Preslab | N/A | Partial Pass | 8/22/2023 Detail 110 for dock leveler. Rebar per plan okay for concrete placement at dock leveler. |
| 08/22/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 8/22/2023 Detail 110 for dock leveler. Rebar per plan okay for concrete placement at dock leveler. |
| 10/24/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 08/22/2023 | COT - HCPL - Rough Soil | N/A | Partial Pass | Relocating 2" main line just out of the fire riser room. 8/22/2023 |
| 10/24/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 11/08/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | -Ok for Level 4 TCO -Need permanent FDC connections -Need Knox FDC caps -Need exterior address numbers -Need Test Header sign above Pump Header |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06798
Permit Description: New Storage Facility
Total Completed Inspections - 23