Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - T22CM06798
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/11/2023 | Water - PDSD | APPROVED | |||
| 09/11/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/09/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
| 08/09/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: T22CM06798 3801 N RUNWAY Zoning I-1 TRANSMITTAL DATE:‎August 9, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: A revision to the development package will be required, please revise DP22-0219 to show the new fire riser room increase If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
| 08/14/2023 | External Reviewers - SAFEBuilt | REVIEW COMPLETED | Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Conditionally Approved Reason: Date Completed : 8/10/2023 4:32:41 PM NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 8/10/2023 1:31:40 PM Mechanical N/A Electrical(E) Reviewer Ron Ross rross@safebuilt.com Conditionally Approved Reason: Date Completed : 8/12/2023 10:01:23 AM Electrical Review of U-Haul By: Ron Ross PE Approved with the following comment that can be addressed in construction. E1.0: Missing Keynote 2 (still shown by PhotoCell) Plumbing N/A |
||
| 08/17/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 08/08/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |